Vendor Name: EE CRUZ & COMPANY INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262804
Current Contract Amount: $30,259,913.50
Spending to Date: $30,259,913.50
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $24,422,968.50 |
04/08/2015 | 12/31/2016 | 151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 04/09/2015 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $684,023.84 |
CO#1-Add Amtrack Force Account Services-151st St. Pedestrian Bridge over Henry Hudson Parkway NYC | 03/10/2016 | |
Amendment | ($131,432.97) |
12/31/2016 | CO# 002, New Items, 151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 06/01/2016 |
Amendment | $129,000.00 |
12/31/2016 | CO# 004, UTILITIES, 151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 11/21/2016 |
Amendment | ($10.00) |
12/31/2016 | CO# 005, Sewer Line, 151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 12/02/2016 |
Amendment | ($10.00) |
12/31/2016 | CO 7 Partnering Workshop New pedestrian bridge 1551 St | 12/16/2016 |
Amendment | ($3.46) |
12/31/2016 | CO 6 larger clevis design proposed Const of new Ped bridge 151 St Region 11 | 12/22/2016 |
Amendment | $0.00 |
11/29/2017 | CO#10-Eleven Month NCTE-151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 02/13/2017 |
Amendment | $244,985.76 |
CO#12 Fabrication of Steel 151st Street Pedestrian Bridge Over Henry Hudson Parkway NYC | 01/19/2018 | |
Amendment | $0.00 |
04/30/2018 | CO#18 Time Extension Construction of new pedestrian Bridge 151st Region 11 | 02/09/2018 |
Amendment | $0.00 |
05/31/2018 | CO#20 NCTE | 05/04/2018 |
Amendment | $1,957,785.00 |
CO#13, New items | 06/04/2018 | |
Amendment | $162,470.00 |
CO#16 Structure Items - Splicing & Ramp Changes | 06/15/2018 | |
Amendment | $0.00 |
06/30/2018 | CO#23, NCTE | 06/22/2018 |
Amendment | ($28.45) |
CO#14, Item increases and decreases. | 07/10/2018 | |
Amendment | $389,928.02 |
CO#17 Additional Landscaping & Utility Fence Access Work | 07/26/2018 | |
Amendment | $289,996.00 |
CO#19 Decrease Item & Overruns & New Guide Rail Items | 08/10/2018 | |
Amendment | $289,967.00 |
CO#21 New/Decrease Items | 08/22/2018 | |
Amendment | $0.00 |
07/31/2018 | CO#24 NCTE | 08/30/2018 |
Amendment | $0.00 |
09/30/2018 | CO#27 NCTE | 10/05/2018 |
Amendment | $519,998.00 |
CO 22 New Fence & Stair & Grate Items | 10/23/2018 | |
Amendment | ($3.00) |
CO#25 New Increase Decrease Items 151st Street Pedestrian Bridge NYC | 01/11/2019 | |
Amendment | $142,425.00 |
CO#26 New Misc Excavation & Concrete Form Items | 03/12/2019 | |
Amendment | $148,360.00 |
CO#29 New Structural Items | 03/28/2019 | |
Amendment | $418,198.00 |
CO#30 Winter Concrete & Earthwork Brick Shelves Junction Box Remove Light Pole Relocate Sign | 04/29/2019 | |
Amendment | $155,385.00 |
CO#31 Additional ADA & Asphalt & Safety Work | 05/16/2019 | |
Amendment | $477,725.00 |
CO#32 West Abutment Approach Slab Formwork Placement of Mulch Remove/Reinstall Benches | 06/05/2019 | |
Amendment | $157,900.00 |
CO#33 New Item Construction of New Pedestrian Bridge Over Henry Hudson Parkway NYC | 07/09/2019 | |
Amendment | ($11.57) |
CO#34 Cleanup | 10/07/2019 | |
Amendment | ($199,702.17) |
CO#35 | 02/28/2020 |