Vendor Name: SLATE HILL CONSTRUCTORS INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262637
Current Contract Amount: $2,457,825.07
Spending to Date: $2,457,825.07
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,674,426.15 |
09/12/2014 | 07/01/2016 | LARGE CULVERT PROJECT CAYUGA OSWEGO & TOMPKINS COUNTIES | 09/12/2014 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $100,000.00 |
CO#01 - FAW, mid Nov. lake effect snow storm, Region 5 - 112 Exempt | 12/12/2014 | |
Amendment | ($67,074.44) |
CO# 002, DECREASE, LARGE CULVERT PROJECT CAYUGA OSWEGO & TOMPKINS COUNTIES | 03/04/2015 | |
Amendment | ($4,889.01) |
CO# 003, Decrease / New Item, Large Culvert Project, Cayuga Oswego & Tompkins Cos | 07/20/2015 | |
Amendment | ($0.02) |
07/01/2016 | CO 5, Increase/Decrease, Large Culvert Project Cayuga, Oswego, & Tompkins Counties | 02/10/2016 |
Amendment | $61,586.63 |
07/01/2016 | CO# 006, EMERGENCY WORK, LARGE CULVERT PROJECT CAYUGA OSWEGO & TOMPKINS COUNTIES | 06/23/2016 |
Amendment | ($72.00) |
07/01/2016 | CO 8 Conventional wingwalls changed to 3 sided inverted units. Region 3 large culvert project | 07/13/2016 |
Amendment | ($306,152.24) |
07/01/2016 | Final Change Order LARGE CULVERT PROJECT CAYUGA OSWEGO & TOMPKINS COUNTIES | 09/30/2016 |
Amendment | $0.00 |
10/31/2016 | CO 10 No cost time extension | 10/25/2016 |
Amendment | $0.00 |
11/18/2016 | CO#11-Two Week NCTE for Remaining Asphalt Work-Large Culvert Project Cayuga Oswego&Tompkins Counties | 11/23/2016 |
Amendment | $0.00 |
11/18/2016 | FINAL, LARGE CULVERT PROJECT CAYUGA OSWEGO & TOMPKINS COUNTIES | 04/12/2017 |