Vendor Name: YONKERS CONTRACTING CO INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D262100
Current Contract Amount: $14,522,069.23
Spending to Date: $14,522,069.23
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $10,243,480.15 |
12/26/2012 | 12/31/2013 | REPLACE TWO INTERSTATE 84 BRIDGES OVER DINGLE RIDGE ROAD PUTNAM COUNTY | 12/26/2012 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $317,341.52 |
CO#2- FAW acceleration of critical bridge construction activities- Putnam Co. | 10/16/2013 | |
Amendment | $273,125.94 |
CO #5-add new item- Replace 2 Interstate 84 bridges over Dingle Ridge Rd - Putnam Co. | 01/03/2014 | |
Amendment | $304,927.45 |
CO#9 Agreed prices & final quantity-Replace two I-84 Bridges over Dingle Ridge Rd, Putnam Co. | 02/28/2014 | |
Amendment | $0.00 |
06/06/2014 | CO #11 NCTE - Replace two I-84 Bridges over Dingle Ridge Rd - Putnam Co. | 03/17/2014 |
Amendment | $39,111.59 |
CO #10 NEW ITEMS FOR TWO I84 BRIDGES OVER DINGLE RD. PUTMAN CO. | 06/11/2014 | |
Amendment | $143,548.01 |
CO# 12 Force Account & Agreed Prices Replace Two Interstate 84 Bridges Ovr Dingle Ridge Rd Putnam Co | 06/20/2014 | |
Amendment | $0.00 |
07/14/2014 | CO# 14 - Replace Two Interstate 84 Bridges Over Dingle Ridge Road Putman County - 5 Week NCTE | 06/26/2014 |
Amendment | $0.00 |
08/29/2014 | CO#16-Six Week NCTE-Replace Two Interstate I-84 Bridges Over Dingle Ridge Road Putman County | 09/03/2014 |
Amendment | $451,511.38 |
CO#13-New & Increased Items-Replace Two Interstate I-84 Bridges Over Dingle Ridge Road Putman County | 10/07/2014 | |
Amendment | $170,227.66 |
CO#15-Add Entrance&Signal Items-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 10/21/2014 | |
Amendment | $349,792.76 |
CO#17-Adding Multiple Minor Items-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 11/20/2014 | |
Amendment | $127,064.85 |
CO#18-Adding Multiple Items-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 03/05/2015 | |
Amendment | $19,586.41 |
CO#19-Item Increases&Decreases-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 04/27/2015 | |
Amendment | $18.13 |
CO#21-Item Underruns&Overruns-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 05/21/2015 | |
Amendment | $292,011.20 |
CO#20-FAW Earthwork Erosion Ctrl-Replace Two Interstate I-84 Bridges Over Dingle Ridge Rd Putman Co | 06/12/2015 | |
Amendment | $11,715.41 |
CO#22-Final Quantity Increases&Decreases-Replace Two I-84 Bridges Over Dingle Ridge Road Putman Co | 07/09/2015 | |
Amendment | $38,384.82 |
08/29/2014 | CO#23-Final Quantity Increases&Decreases-Replace Two I-84 Bridges Over Dingle Ridge Road Putman Co | 02/11/2016 |
Amendment | $144,545.94 |
08/29/2014 | CO#25-Equitable Adjustment&Credit Item-Replace Two I-84 Bridges Over Dingle Ridge Road Putman County | 06/30/2016 |
Amendment | $703,293.76 |
08/29/2014 | CO#27-Temporary Shoring Structure-Replace Two I-84 Bridges Over Dingle Ridge Road Putman County | 08/23/2016 |
Amendment | $541,389.00 |
08/29/2014 | CO#28-Temporary Crane Platforms - Replace Two I-84 Bridges Over Dingle Ridge Road Putman County | 09/01/2016 |
Amendment | $128,345.60 |
08/29/2014 | CO#24-Misc(Finalize Dispute Resolution)-Replace Two I-84 Bridges Over DingleRidge Road Putman County | 09/20/2016 |
Amendment | $405,962.19 |
08/29/2014 | CO#26-Claim Settlement-OH Compensation-Replace 2 i-84 Bridges Over Dingle Ridge Road Putman County | 12/07/2016 |
Amendment | ($183,314.54) |
08/29/2014 | CO 29 Final Payment Reconciliations Replacement of 1-84 Bridges over Dingle Ridge Rd Region 8 | 03/02/2017 |