Vendor Name: KISKA CONSTRUCTION LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D261778
Current Contract Amount: $17,968,696.27
Spending to Date: $17,968,696.25
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date | |
---|---|---|---|---|---|---|
Original Contract data not available for this contract record. |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $618,178.57 |
CO#2 | 11/14/2012 | |
Amendment | $166,490.44 |
shim course hot mix asphalt | 03/01/2013 | |
Amendment | $190,281.53 |
CO# 5 - extra work | 08/30/2013 | |
Amendment | $0.00 |
01/23/2014 | ncte | 09/19/2013 |
Amendment | $1,216,886.70 |
maintenance of 54 bridges, joint/bearing repairs | 10/17/2013 | |
Amendment | $140,425.95 |
CO#10 - add'l cost in milling, pavement markings, incidental construction @ Bridge 56 piers 7, 8 & 9 | 11/22/2013 | |
Amendment | $0.00 |
06/30/2014 | CO 14 NCTE Orange and Rockland Co's | 02/13/2014 |
Amendment | $241,683.39 |
CO#11 - Force Account Estimate for Pedistal Modifications @ Bridge 56 | 02/18/2014 | |
Amendment | $294,080.14 |
CO 12 increase and decreases & additional cost due to no RR agreement | 03/04/2014 | |
Amendment | $760,792.60 |
CO 13 increase in items; temporary shielding/platform and sidewalk joint repair - Orange/Rockland Co | 04/15/2014 | |
Amendment | $94,022.28 |
CO#15 - FAW retrofit plates on bridge 56 | 04/29/2014 | |
Amendment | $18,559.34 |
CO 16 new and overruns, and adjustments | 05/28/2014 | |
Amendment | $0.00 |
07/31/2014 | CO 20 No cost time extension | 07/03/2014 |
Amendment | $135,002.61 |
CO 17 FAW Bridges 55,46, 56 scaffold brdige 56 pier 9 Reion 8 | 09/12/2014 | |
Amendment | ($113,657.02) |
CO 18 Pedestal Modificatin parts A-E Region 8 | 09/30/2014 | |
Amendment | $3,335.29 |
CO WORK FOR VARIOUS BRDIGES Reg 08 | 10/21/2014 | |
Amendment | $5,316.00 |
CO 21 retrofit plates on bridge 56 Region 8 | 12/18/2014 | |
Amendment | ($322,569.47) |
Maintenance by contract 54 bridges Rockland/Orange Co's Region 8 | 02/05/2015 | |
Amendment | ($75,498.83) |
Co 23 Over and under runs, Bridge 56 Winter concrete pt 2,3, and final paint Region 8 | 02/19/2015 | |
Amendment | ($101,395.90) |
CO 24 OVERRUNS AND UNDERRUNS Region 8 | 04/22/2015 | |
Amendment | $346,561.93 |
CO 26 Claim settlements and extra work region 08 | 08/05/2015 | |
Amendment | $292,979.03 |
CO 27 Claim settlement, supplemental APJ material needed Maint 54 bridges Region 8 | 09/21/2015 | |
Amendment | $458,810.18 |
07/31/2014 | CO#28 Admin Settlements WZTC Costs - Maintenance by Contract 54 Bridges in Rockland & Orange Co | 12/14/2015 |
Amendment | $911.51 |
Change order #29 cleanup | 02/12/2021 |