Vendor Name: CCI COMPANIES INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D261425
Current Contract Amount: $7,395,731.82
Spending to Date: $7,395,731.82
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date | |
---|---|---|---|---|---|---|
Original Contract data not available for this contract record. |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $45,068.29 |
Rehab Rte 104 George St to Kocher Oswego CO CO 1 | 05/11/2012 | |
Amendment | $142,864.73 |
CO#3 | 05/24/2012 | |
Amendment | $37,273.69 |
OOC#4 | 09/20/2012 | |
Amendment | $88,028.09 |
CO#5 asphalt and fuel price adjment | 02/22/2013 | |
Amendment | $318,086.67 |
CO# 6 - CONTRACT QUANTITY OVERRUNS | 05/28/2013 | |
Amendment | $8,507.36 |
FORCE ACCOUNTS | 06/13/2013 | |
Amendment | $10,587.78 |
lighting, ROW marker | 06/24/2013 | |
Amendment | $6,881.36 |
FORCE ACCOUNT WORK CO 08 | 07/08/2013 | |
Amendment | $14,274.08 |
FORCE ACCOUNT CO 10 | 07/12/2013 | |
Amendment | $11,774.40 |
FORCE ACCOUNT | 07/23/2013 | |
Amendment | $11,489.72 |
FORCE ACCOUNT | 08/02/2013 | |
Amendment | $10,333.33 |
FAW light plant rental charge | 09/03/2013 | |
Amendment | $1,265.07 |
CO 13 | 09/09/2013 | |
Amendment | $7,654.79 |
FORCE ACCOUNT | 09/18/2013 | |
Amendment | $10,339.14 |
FORCE ACCOUNT | 09/23/2013 | |
Amendment | $26,253.42 |
FORCE ACCOUNTS | 09/27/2013 | |
Amendment | $28,883.35 |
FORCE ACCOUNTS | 10/03/2013 | |
Amendment | ($19,763.79) |
drainage, signs, utilities CO 20 | 10/18/2013 | |
Amendment | $5,027.69 |
FORCE ACCOUNTS | 11/05/2013 | |
Amendment | $82,306.56 |
CO#21 - CHANGES IN CONTAMINATED SOILS | 11/22/2013 | |
Amendment | $4,765.17 |
traffic signals Co 22 | 12/06/2013 | |
Amendment | ($362,052.00) |
rehab / widen Rte 104 George St to Kocher | 12/20/2013 | |
Amendment | $79,165.20 |
CO#27 Tree removal, planting, temporary mulch | 01/15/2014 | |
Amendment | ($8,990.89) |
CO 28 clean up order Oswego | 01/31/2014 | |
Amendment | $23,297.48 |
CO30 earth work,dry swale redesign,rock excavationpipe run,milling sewer cleanout,utilites | 02/06/2014 | |
Amendment | $1,832.74 |
CO 32 Traffic extra work | 04/09/2014 | |
Amendment | $11,834.19 |
CO 33 PICTURE FRAMING DISPUTE | 06/17/2014 | |
Amendment | $23,906.71 |
CO 34 CLEANUP CHANGE ORDER | 06/24/2014 | |
Amendment | $3,886.62 |
FORCE ACCOUNT REGIONAL DISPUTE | 10/29/2014 | |
Amendment | ($1,006,565.18) |
CO 30 CLEANUP NEGATIVE ITEM CHANGE ORDER Region 3 | 11/13/2014 | |
Amendment | $5,330.18 |
FORCE ACCOUNT REGIONAL DISPUTE | 11/19/2014 | |
Amendment | ($8,445.47) |
CO 38 FUEL & ASPHALT FINAL ADJUSTMENT Region 3 | 01/30/2015 | |
Amendment | $5,928.62 |
03/31/2013 | CO 39 Downtime for rock excavation Rehab of Rte 104 Region 3 | 01/14/2016 |
Amendment | ($11,249.77) |
03/31/2013 | CO#40. Clean up CO, rehab Rte 104 George St to Kocher, Oswego Cnty | 03/15/2016 |
Amendment | ($0.01) |
03/31/2013 | FINAL, rehab Rte 104 George St to Kocher, Oswego Cnty | 01/06/2017 |