Vendor Name: BURGIO & CAMPOFELICE INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006812
Current Contract Amount: $6,192,657.00
Spending to Date: $5,433,463.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $6,059,451.00 |
03/29/2023 | 05/23/2025 | Mechanical systems upgrade for Butler Library at SUNY Buffalo | 04/17/2023 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
06/13/2025 | Term correction based on notice to proceed | 04/20/2023 |
Amendment | $81,210.00 |
Change orders 1 and 2 scope revision and remove additional wall areas and asbestos abatement | 01/12/2024 | |
Amendment | ($285.00) |
Change order three for field order allowance reduction | 04/05/2024 | |
Amendment | $43,352.00 |
Change orders four, five, six and seven for various mechanical system upgrades | 04/19/2024 | |
Amendment | $4,912.00 |
Change order eight is for a in-line exhaust fan and removal of dampers | 04/25/2024 | |
Amendment | $4,017.00 |
Change order nine to provide trim kits for diffusers | 05/08/2024 |