Vendor Name: NORTHLAND ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006787
Current Contract Amount: $41,519,995.00
Spending to Date: $20,359,048.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $41,226,000.00 |
01/24/2023 | 05/07/2026 | Renovate Hewitt Hall phase 2 at SUNY Oswego | 02/10/2023 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
05/30/2026 | Update contract dates per notice to proceed | 02/17/2023 |
Amendment | $175,842.00 |
Change order one is for lead paint remediation | 02/07/2024 | |
Amendment | $99,205.00 |
Change order two for additional steel reinforcement at floor penetrations | 03/19/2024 | |
Amendment | $8,657.00 |
Change order number three to change voice over booth to podcast studio | 05/02/2024 | |
Amendment | $10,291.00 |
Change order number four for lead paint remediation on existing steel structure | 05/03/2024 |