Vendor Name: STREETER ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006772
Current Contract Amount: $7,195,874.00
Spending to Date: $6,163,155.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $5,882,000.00 |
11/10/2022 | 04/21/2025 | Abatement and window replacement at Sturgess Hall, SUNY Geneseo | 11/22/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
05/11/2025 | Term correction based on notice to proceed | 12/05/2022 |
Amendment | ($613.00) |
Change order one is a credit for temporary wall and door | 09/06/2023 | |
Amendment | ($150,000.00) |
Change order two is to reduce the field order allowance | 01/12/2024 | |
Amendment | $36,000.00 |
Change order three is to repoint the mason joints | 02/14/2024 | |
Amendment | $16,063.00 |
Change orders four and five for repointing of masonry joints | 02/21/2024 | |
Amendment | ($1,797.00) |
Change order six for credit for not abating and removing vestibule plaster walls and ceiling | 04/19/2024 | |
Amendment | $48,792.00 |
Change orders seven through 11 are for various changes | 05/02/2024 | |
Amendment | $1,000,032.00 |
Change orders 12-13 for removal of slag and existing concrete topping | 05/16/2024 | |
Amendment | $194,481.00 |
Change order 14 is to repair 63 masonry window jambs | 05/23/2024 | |
Amendment | ($33,180.00) |
Change order 15 to provide a credit for elimination of concrete slab infill | 06/07/2024 | |
Amendment | $0.00 |
09/20/2025 | Change order 16 extension of completion date due to unforseen conditions | 08/16/2024 |
Amendment | $208,095.00 |
Change orders 17, 18 and 19 for additional removal and repair of window jambs | 09/04/2024 | |
Amendment | ($3,999.00) |
Change order 20 credit for elimination of femolition under asbestos abatement | 09/13/2024 |