Vendor Name: SCHENECTADY HARDWARE & ELEC CO INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45583E
Current Contract Amount: $6,884,951.00
Spending to Date: $691,836.30
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $6,513,752.00 |
05/20/2022 | 08/02/2025 | Replace Switchgear Empire State Plaza Albany county | 05/20/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $172,318.00 |
CO#1 78307 quick connect board | 06/07/2023 | |
Amendment | $0.00 |
02/25/2026 | CO#2 78764 No cost time extension | 06/09/2023 |
Amendment | $150,000.00 |
CO #3 78398 Provide premium time for shutdown work | 07/26/2023 | |
Amendment | $48,881.00 |
CO#4 79007 Cable pit splices and adding junction modules | 10/04/2023 |