Vendor Name: NORTHLAND ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006751
Current Contract Amount: $3,093,837.00
Spending to Date: $3,047,236.00
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,812,000.00 |
05/11/2022 | 05/10/2024 | Replace canopy at the University Hospital's Emergency Department entrance | 05/24/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
05/25/2024 | Update the contract term | 05/27/2022 |
Amendment | $4,225.00 |
Change order #1 is to provide additional N02 monitoring and alternate canopy exhaust fan | 02/09/2023 | |
Amendment | $12,255.00 |
Change order #2 is to provide vertical ceiling panels for the drop in ceiling height for sprinklers | 02/16/2023 | |
Amendment | $2,216.00 |
Change order #3 is to provide new granite curbing | 04/13/2023 | |
Amendment | $85,969.00 |
Change orders #4 and 5 removal of granite curbing and other changes | 05/31/2023 | |
Amendment | $3,214.00 |
Change order 6 is to provide and install 3 pole 600VAC 20A breaker and radius granite curbs | 07/13/2023 | |
Amendment | $37,362.00 |
Change order 7 and 8 for various changes | 08/10/2023 | |
Amendment | $1,020.00 |
Change order nine for new lighting | 08/18/2023 | |
Amendment | $20,652.00 |
Change order 10 - remove asphalt base layer encountered below existing contrete pavers | 10/04/2023 | |
Amendment | $84,052.00 |
Change orders 11 and 12 for additional drainage and other changes | 12/12/2023 | |
Amendment | $30,872.00 |
Change order 13 for additional asphalt paving work and barriers | 04/12/2024 |