Vendor Name: MLB CONSTRUCTION SERVICES LLC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006729
Current Contract Amount: $17,399,165.00
Spending to Date: $16,719,670.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $16,777,900.00 |
04/07/2022 | 01/05/2025 | Renovation of Memorial Hall at SUNY Plattsburgh | 04/13/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
01/17/2025 | Term correction | 04/20/2022 |
Amendment | $16,430.00 |
Change orders #1-3 drain installation, credit for equipment modifications and electrical changes | 01/06/2023 | |
Amendment | $8,726.00 |
Change order #4 is to provide modification to wireless access point infrastructure | 01/11/2023 | |
Amendment | $191,292.00 |
Change order #5 is to provide modification and abatement to hazardous material | 04/11/2023 | |
Amendment | ($15,702.00) |
Change orders #6 and #7 for various changes | 04/20/2023 | |
Amendment | $74,474.00 |
Change orders 8 and 9 are to modify gym folding partition, bleacher graphics, HVAC and walls | 05/30/2023 | |
Amendment | ($200,000.00) |
Change order 12 is to reduce the field order allowance | 07/10/2023 | |
Amendment | $128,838.00 |
Change orders 10 and 11 are for various changes | 07/26/2023 | |
Amendment | $38,406.00 |
Change order 13 for drywall modifications | 08/06/2023 | |
Amendment | ($119,386.00) |
Change order 14 is a deductive for various changes | 08/31/2023 | |
Amendment | $7,134.00 |
Change order 15 is to modify the basketball backstop supporting steel | 09/15/2023 | |
Amendment | $38,677.00 |
Changer orders 16, 17, 18 and 19 for various changes | 10/16/2023 | |
Amendment | $51,278.00 |
Change orders 20, 21, and 22 for various changes | 11/06/2023 | |
Amendment | $77,273.00 |
Change order 24 and 25 for various changes | 12/08/2023 | |
Amendment | $79,704.00 |
Change order 23 and 26 for various changes | 01/10/2024 | |
Amendment | $85,712.00 |
Change orders 27, 28 and 30 various changes | 03/01/2024 | |
Amendment | $126,673.00 |
Change orders 29 and 31-34 are for various changes | 03/14/2024 | |
Amendment | $31,736.00 |
Change orders 35 and 36 to modify canopy framing and provide new knee wall and floor transition | 04/16/2024 |