Vendor Name: MARK CERRONE INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006709
Current Contract Amount: $11,450,563.00
Spending to Date: $10,779,058.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $10,813,000.00 |
03/04/2022 | 11/13/2024 | Infrastructure improvements- phase 2 on North Campus at SUNY Brockport | 03/14/2022 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
11/30/2024 | Term correction | 03/23/2022 |
Amendment | $59,032.00 |
Change orders one and two for partial parking lot reconstruction | 09/07/2023 | |
Amendment | $43,419.00 |
Change order 3 for additional signage and ADA curb alterations | 09/12/2023 | |
Amendment | $43,951.00 |
Change orders 4-8 for various changes | 10/24/2023 | |
Amendment | $11,848.00 |
Change order 10 for removal of underground fuel storage tanks | 11/17/2023 | |
Amendment | $70,632.00 |
Change orders 9 and 11 through 15 for various changes | 12/14/2023 | |
Amendment | $432,944.00 |
Change orders 16 through 20 for various changes | 02/12/2024 | |
Amendment | $8,440.00 |
Change order 21 for curb ramp and walkway | 02/21/2024 | |
Amendment | ($32,703.00) |
Change order 22 provides credit associated with asbestos piping removal | 02/29/2024 |