Vendor Name: AOW ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006685
Current Contract Amount: $3,561,692.00
Spending to Date: $3,341,635.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,971,700.00 |
12/07/2021 | 12/11/2023 | Renovate gym & infill pool in the Physical Education Building Albany campus | 12/14/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
12/21/2023 | revise term based on notice to proceed | 12/20/2021 |
Amendment | ($840.00) |
Change order #1 abatement corrections | 06/07/2022 | |
Amendment | $7,504.00 |
Change order #2 for additional roll down divider graphics | 06/24/2022 | |
Amendment | $579.00 |
Change order #3 - graphic wrap five columns | 09/09/2022 | |
Amendment | $138,131.00 |
Change order No. 4 and No. 5 for PCB caulk abatement and new transformer with electrical panels | 11/16/2022 | |
Amendment | $131,839.00 |
Change order #6 provide for the leveling of existing gymnasium floor | 12/15/2022 | |
Amendment | $74,018.00 |
Change order 7 for floor boxes at the scorer's tables | 03/09/2023 | |
Amendment | $183,422.00 |
Change orders #7, #9, #10 and #11 are for various changes | 04/06/2023 | |
Amendment | $26,938.00 |
Change orders 12 and 13 for various changes | 02/29/2024 | |
Amendment | $0.00 |
05/01/2025 | No cost time extension for guarantee period | 03/06/2024 |
Amendment | ($682.00) |
Change order 15 to reduce the contract field order allowance | 03/15/2024 | |
Amendment | $29,083.00 |
Change order 14 & 16 are to relocate doors and revise signage | 03/26/2024 |