Vendor Name: ACS SYSTEM ASSOCIATES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D46220H
Current Contract Amount: $950,580.00
Spending to Date: $897,168.59
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $780,900.00 |
11/30/2021 | 04/13/2023 | Rehabilitate armory & storage building Bronx Armory Bronx County | 11/30/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
08/09/2023 | CO 1 78010 No cost time extension | 11/09/2022 |
Amendment | $19,517.00 |
CO#2 77883 ductwork changes affected by ceiling heights | 12/05/2022 | |
Amendment | $18,361.00 |
CO 4 77918 Provide cost and material to relocate the condensate pipes | 02/23/2023 | |
Amendment | $10,892.00 |
CO #5 78016 Storage building boiler repairs | 03/01/2023 | |
Amendment | $31,281.00 |
CO#7 78320 Provide unit heater. | 05/17/2023 | |
Amendment | $5,924.00 |
CO#8 78532 Added ventilation requirements. | 05/22/2023 | |
Amendment | $61,310.00 |
CO#6 78128 provide & install cast iron radiators where existing radiators were removed | 06/12/2023 | |
Amendment | $5,006.00 |
CO#9 78569 Relocate wall mounted unit | 08/02/2023 | |
Amendment | $7,147.00 |
CO#11 78812 Fire damper for exhaust duct | 08/21/2023 | |
Amendment | $0.00 |
05/20/2024 | CO#10 78979 No cost time extension | 09/07/2023 |
Amendment | $6,577.00 |
CO #12 78891 Update steam boiler controls | 10/18/2023 | |
Amendment | $3,665.00 |
CO #13 79323 Additional pipe insulation | 01/17/2024 |