Vendor Name: NORTHLAND ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006680
Current Contract Amount: $3,058,075.00
Spending to Date: $3,058,075.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,699,000.00 |
11/10/2021 | 05/29/2023 | Rehabilitate 4th Floor of Bray Hall at SUNY ESF | 11/26/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
06/20/2023 | revise term based on notice to proceed | 12/03/2021 |
Amendment | $132,960.00 |
Change order #1 provide for reroute of chilled water piping | 06/09/2022 | |
Amendment | $17,138.00 |
Change order #2- relocate existing electrical infrastructure | 08/30/2022 | |
Amendment | $3,643.00 |
Change order #3 added two control panels to the hydronic leak detection system | 10/17/2022 | |
Amendment | $11,681.00 |
Change order #4 replace light two light fixtures, relocate smoke detector and other changes | 11/04/2022 | |
Amendment | $18,598.00 |
Change order #5 to provide heat trace system and drain valve at the specified adiabatic cooler | 11/22/2022 | |
Amendment | ($2,585.00) |
Change order #6 is to close out the field order allowance | 11/22/2022 | |
Amendment | $74,183.00 |
Change orders #7-8 reroute chilled water piping and provide components at heat pumps | 12/08/2022 | |
Amendment | $29,713.00 |
Change order #9 to add binder thickness, adjust underground piping and revise power feeds | 01/19/2023 | |
Amendment | $10,250.00 |
Change order #10 is to revise lighting controls, wire and breaker | 02/01/2023 | |
Amendment | $24,314.00 |
Change order #11 is to delete specified boiler and replace with three smaller boilers | 02/16/2023 | |
Amendment | $32,846.00 |
Change order #12 provide boiler heat exchanger and piping | 06/02/2023 | |
Amendment | $6,334.00 |
Change order 13 provide breaker for added heat trace system and other repairs | 09/01/2023 |