Vendor Name: ALL STATE BOILER & CONSTRUCTION INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006678
Current Contract Amount: $2,694,022.00
Spending to Date: $2,474,370.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,632,000.00 |
10/15/2021 | 10/15/2023 | Install backflow prevention and pump station at SUNY Purchase Westchester County | 10/21/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
11/02/2023 | Term correction | 11/03/2021 |
Amendment | $43,403.00 |
Change order #1 is to provide a temporary overland water bypass | 02/08/2023 | |
Amendment | ($733.00) |
Change order two for removal of gas curb valve and curb box | 03/23/2023 | |
Amendment | ($10,508.00) |
Change Order #3 to reduce the Field Order Allowance | 05/05/2023 | |
Amendment | $14,223.00 |
Change order #4 for temporary variable frequency drive for the 125 HP booster pump | 05/17/2023 | |
Amendment | $2,764.00 |
Change order 5 for additional redundant pump discharge pressure transducer | 09/18/2023 | |
Amendment | $12,873.00 |
Change order number six for modifications to existing radio telemetry | 03/04/2024 |