Vendor Name: BUTLER CONSTRUCTION GROUP INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45919C
Current Contract Amount: $2,199,949.00
Spending to Date: $1,440,698.79
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,021,641.00 |
08/27/2021 | 08/20/2022 | Provide municipal sewer connections Rockland PC Hudson River Campus Poughkeepsie Dutchess County | 08/27/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $40,910.00 |
Change order #1 76441 addition of sewer flow meter | 01/12/2022 | |
Amendment | $42,840.00 |
CO# 2 77189 Correction of manhole for existing sewer plug | 06/09/2022 | |
Amendment | $0.00 |
02/26/2023 | CO#3 77722 No cost time extension | 10/20/2022 |
Amendment | $32,516.00 |
CO #4 78394 Hydrostatic manhole testing | 03/29/2023 | |
Amendment | $20,213.00 |
CO#5 78428 Asbestos pipe removal & install ferno couplings | 05/11/2023 | |
Amendment | $41,829.00 |
CO#6 78506 new pipe in conflict with existing sewer line & additional manhole waterproofing | 05/26/2023 | |
Amendment | $0.00 |
09/15/2023 | CO#7 79371 No cost time extension | 12/29/2023 |