Vendor Name: BILLITIER ELECTRIC INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006633
Current Contract Amount: $836,226.00
Spending to Date: $836,226.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $818,900.00 |
07/15/2021 | 12/12/2022 | Upgrade site lighting campus-wide at SUNY Cortland phase 2 | 08/04/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
01/08/2023 | Contract term update | 08/12/2021 |
Amendment | ($22,670.00) |
Change order #2 to close out the remaining field order allowance | 11/07/2022 | |
Amendment | ($3,932.00) |
Change order #3 is a deductive for abatement work not performed | 12/21/2022 | |
Amendment | $34,219.00 |
Change order 4 for replacement of five lighting poles and bases | 12/23/2022 | |
Amendment | $9,709.00 |
Change order 1 for additional electrical charges to tower blue lights and panels | 06/29/2023 |