Vendor Name: MICHAEL A FERRAUILO PLUMBING & HEATING INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: DEE584H
Current Contract Amount: $600,000.00
Spending to Date: $398,881.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $300,000.00 |
06/11/2021 | 10/09/2021 | Repair failed piping and equipment Building 136 Willard Drug Treatment Center | 07/09/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $300,000.00 |
CO#1 76746 Additional funds condensate pumps receiver & water inlet system | 01/18/2022 | |
Amendment | $0.00 |
02/09/2022 | Change order #2 67980 no cost time extension | 02/28/2022 |