Vendor Name: AOW ASSOCIATES INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006641
Current Contract Amount: $3,685,641.00
Spending to Date: $3,685,641.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $3,540,500.00 |
06/15/2021 | 09/13/2023 | Bouck Hall renovation at bookstore and related student life | 06/18/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
09/26/2023 | Term correction | 06/29/2021 |
Amendment | $774.00 |
Change order 1 - Remove masonry wall to allow installation of new mechanical equipment in room BH17D | 11/19/2021 | |
Amendment | $2,671.00 |
Change order to replace the men's locker room door | 11/26/2021 | |
Amendment | $29,206.00 |
Provide removal and replacement of corridor flooring per RFP | 12/10/2021 | |
Amendment | ($315.00) |
Modify the hand sinks - CO#4 | 04/13/2022 | |
Amendment | ($502.00) |
Change order #5- delete rubber base pre-formed corners | 08/24/2022 | |
Amendment | $23,761.00 |
Change order #6 provide additional data and camera infrastructure | 11/08/2022 | |
Amendment | $17,171.00 |
Change order #7 phase two window bulkhead design and additional credits | 11/09/2022 | |
Amendment | ($9,770.00) |
Change order #8 modify chilled water pipe layout and changes to millwork and plumbing fixtures | 11/15/2022 | |
Amendment | $6,995.00 |
Change order #9 to pull new data cabling to the theater and gym | 11/22/2022 | |
Amendment | $57,674.00 |
Change Order #10 is for HVAC modifications in the training suite | 12/08/2022 | |
Amendment | ($1,926.00) |
Change order #11 is a deductive to delete light fixtures in the temporary bookstore | 01/06/2023 | |
Amendment | ($1,828.00) |
Change order #12 is to reduce contract field order allowance | 02/14/2023 | |
Amendment | $21,230.00 |
Change order #13 is for fire protection modification and miscellaneous plumbing and electric | 03/06/2023 |