Vendor Name: JERSEN CONSTRUCTION GROUP LLC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45857C
Current Contract Amount: $15,257,602.00
Spending to Date: $13,966,459.47
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $14,521,900.00 |
05/28/2021 | 12/31/2023 | Rehabilitate wastewater treatment plant Eastern CF Ulster County | 05/28/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $28,015.00 |
CO#1 76548 Slab replacement and reinforcement | 12/21/2021 | |
Amendment | $41,976.00 |
Change order #2 76609 add emergency backup power source | 02/01/2022 | |
Amendment | $0.00 |
04/11/2024 | CO # 5 77349 No cost time extension | 06/10/2022 |
Amendment | $18,789.00 |
CO #6 77070 increase for elevation adjustment | 06/17/2022 | |
Amendment | $70,260.00 |
CO#3 77172 Construction painting interior | 08/30/2022 | |
Amendment | $254,874.00 |
CO#4 76678 installation & utility modifications for office trailer & asphalt parking lot | 09/08/2022 | |
Amendment | $92,655.00 |
CO#7 77656 Purchase office trailer & furniture & equipment | 11/08/2022 | |
Amendment | $11,975.00 |
CO #8 76789 Reimbursement for equipment | 07/06/2023 | |
Amendment | $25,585.00 |
CO #9 78904 increase for additional concrete samples | 10/20/2023 | |
Amendment | $595.00 |
CO#12 79111 provide spare sample pump | 10/26/2023 | |
Amendment | $41,612.00 |
CO#10 78965 Watermain location | 11/06/2023 | |
Amendment | $24,749.00 |
CO #11 78989 Increases in labor & supplies | 11/16/2023 | |
Amendment | $5,685.00 |
CO#13 79005 Increase holding capactiy of manhole | 12/06/2023 | |
Amendment | $22,380.00 |
CO#14 79105 Additional piping reconfiguration | 02/08/2024 | |
Amendment | $0.00 |
09/02/2024 | CO# 18 78965A No cost time extension | 02/14/2024 |
Amendment | $2,300.00 |
CO#15 78989A Amends change order Seq 15 due to radius rail cost increase | 02/21/2024 | |
Amendment | $10,777.00 |
CO#21 79613 ACM abatement | 03/26/2024 | |
Amendment | $0.00 |
12/12/2024 | CO# 26 79872 No cost time extension | 04/12/2024 |
Amendment | $48,955.00 |
CO #23 79713 Drainage | 04/18/2024 | |
Amendment | $34,520.00 |
CO #79597 tank drainage and cleaning | 05/02/2024 |