Vendor Name: MARK CERRONE INC
Agency Name: State University Construction Fund
Department/Facility Name: State University Construction Fund
Contract Number: D006622
Current Contract Amount: $3,300,877.00
Spending to Date: $3,300,877.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $3,288,000.00 |
04/07/2021 | 02/28/2023 | Reconstruct central heating plant remove underground tanks and boilers SUNY Buffalo Erie County | 04/15/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
03/12/2023 | Term correction | 04/21/2021 |
Amendment | $0.00 |
06/30/2023 | Extension of 110 days | 12/23/2021 |
Amendment | $3,762.00 |
Change order #2 abate asbestos containing valve insulation and gaskets | 01/20/2022 | |
Amendment | $71,118.00 |
08/12/2023 | Change order #s 3,4 and 5- replace additional breeching, steel door and time extension | 10/13/2022 |
Amendment | $2,166.00 |
Change order #6 for additional costs for construction trailer and related items | 02/28/2023 | |
Amendment | ($64,169.00) |
Change order 7 is to reduce contract field order allowance | 08/18/2023 |