Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $10,297,000.00 |
03/30/2021 | 02/18/2024 | Rehab mechanical systems & operating rooms at Downstate Health Science University, Kings County | 04/12/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
03/05/2024 | Update the contract term | 04/19/2021 |
Amendment | $512,409.00 |
Change orders 1-6 for scope of work adjustments | 10/08/2021 | |
Amendment | $19,121.00 |
Change Order #8 - Reposition four variable frequency drives and replace deteriorated piping | 12/03/2021 | |
Amendment | $66,912.00 |
Change order #7 HVAC reheat piping work | 12/03/2021 | |
Amendment | $69,664.00 |
Replacement of the reheat piping | 12/15/2021 | |
Amendment | $4,505.00 |
Change order #9 replace low pressure steam bypass valves at the cooling tower | 01/06/2022 | |
Amendment | $74,602.00 |
Change orders #11-13 for replacement of mechanical equipment and pipe rerouting | 02/24/2022 | |
Amendment | $496,462.00 |
Change order #14 to replace mechanical equipment | 03/24/2022 | |
Amendment | $21,745.00 |
Change order #15 update components of the air handling units | 05/12/2022 | |
Amendment | $39,699.00 |
Change orders# 17-18 provide additional switches in restrooms and provide power to automatic doors | 06/30/2022 | |
Amendment | $50,644.00 |
Change order #19 - electrical testing and campus change requests | 07/14/2022 | |
Amendment | $14,523.00 |
Change order #16 provide additional work for isolation rooms | 07/20/2022 | |
Amendment | $6,930.00 |
Change order #20 modifications to the electric coordination study | 08/17/2022 | |
Amendment | $97,821.00 |
Change order #21 replace ceilings in two isolation rooms | 10/07/2022 | |
Amendment | $106,280.00 |
Change orders #22-23 for isolation valve installation and mechanical equipment replacement | 12/15/2022 | |
Amendment | $42,988.00 |
Change order #24 wall and ceiling repair and reheat blockage mitigation | 04/10/2023 | |
Amendment | $23,043.00 |
Change order 25 and 26 for materials and labor | 07/31/2023 | |
Amendment | $578,399.00 |
Change order 27 for HVAC repairs | 08/14/2023 | |
Amendment | $114,838.00 |
Change order 28 is to provide filtration equipment | 08/31/2023 | |
Amendment | $1,669.00 |
Change order number 29 for touchless door operators | 03/01/2024 | |
Amendment | $0.00 |
09/06/2025 | No cost time extension for guarantee period | 03/22/2024 |
Amendment | $187,986.00 |
Change order 30 replace mechanical equipment | 04/12/2024 |