Vendor Name: C P WARD INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D264405
Current Contract Amount: $5,641,181.86
Spending to Date: $5,156,881.88
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $4,414,740.25 |
02/18/2021 | 12/31/2022 | Bridge deck preventative maintenance 8 locations Monroe & Orleans Counties | 02/18/2021 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $8,982.36 |
CO#1 New items rigid plastic conduit & pull box circular reinforce concrete & conduit excavation | 08/10/2021 | |
Amendment | $612.00 |
CO#2 Item increases and decreases | 08/25/2021 | |
Amendment | $19,289.22 |
CO # 3 Addition of box beam guide rail assembly | 08/31/2021 | |
Amendment | $185,000.00 |
CO#7 Adding fascia bracket item | 10/06/2021 | |
Amendment | $69,013.51 |
CO#9 Item increases due to overruns | 12/20/2021 | |
Amendment | $31,085.09 |
CO#11 Temporary barrier & railroad access | 02/08/2022 | |
Amendment | $55,571.55 |
CO#10 New items for vegetation control strip & rebar modification & joint seal correction | 02/17/2022 | |
Amendment | $160,733.20 |
CO#12 Fascia barrier removal work force account work & overruns | 05/11/2022 | |
Amendment | $55,706.30 |
CO #13 | 06/09/2022 | |
Amendment | $53,814.55 |
CO#14 Reinforcing bar exposure underruns | 07/15/2022 | |
Amendment | $40,922.31 |
CO #15 Temporary positive barrier & HMA top course | 08/01/2022 | |
Amendment | $3,187.30 |
CO#16 item overruns | 09/27/2022 | |
Amendment | $9,058.58 |
CO#18 New traffic control items | 10/12/2022 | |
Amendment | $36,519.71 |
CO #20 New items & increases | 01/17/2023 | |
Amendment | $73,137.71 |
CO#21 new items & overruns | 02/03/2023 | |
Amendment | $27,387.60 |
CO #22 Full diamond grinding of structural slab | 02/16/2023 | |
Amendment | $396,420.62 |
CO#23 New items | 05/03/2023 |