Vendor Name: SOUTHEAST MECHANICAL CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45917H
Current Contract Amount: $1,347,149.00
Spending to Date: $1,220,025.04
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,348,115.00 |
11/03/2020 | 12/07/2021 | Replace Tumble Chiller 1 & 2 Building No 144 Cook Chill Production Center Orangeburg Rockland County | 11/03/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
03/21/2022 | Change order #1 75949 no cost time extension | 05/17/2021 |
Amendment | $0.00 |
06/19/2022 | CO #2 76281 No cost time extension | 08/02/2021 |
Amendment | $0.00 |
10/09/2022 | CO #4 77224 No cost time extension | 05/11/2022 |
Amendment | ($966.00) |
CO#3 77144 Credit to replace ice water flow balancing valves w automatic flow balancing valves | 06/09/2022 | |
Amendment | $0.00 |
11/08/2022 | CO#5 77224A No cost time extension | 06/29/2022 |
Amendment | $0.00 |
01/10/2024 | CO #6 79338 No cost time extension | 11/01/2023 |
Amendment | $0.00 |
04/01/2024 | CO #7 79837 No cost time extension | 03/26/2024 |