Vendor Name: CON-TECH BUILDING SYSTEMS INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D46136C
Current Contract Amount: $11,792,571.00
Spending to Date: $10,497,477.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $10,218,300.00 |
09/04/2020 | 08/14/2022 | Classroom & office space buildings 8 10 11 Residential Rehab Unit Upstate CF Franklin County | 09/04/2020 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($19,803.00) |
CO#1 75549 detention hardware & control consoles | 04/23/2021 | |
Amendment | $7,073.00 |
CO#6 76224 adds funding control console countertop extension | 08/30/2021 | |
Amendment | ($67,210.00) |
CO #2 76153 credit to remove painting | 09/03/2021 | |
Amendment | ($1,240.00) |
CO# 3 76154 Removal of door closer from staff interview door | 09/07/2021 | |
Amendment | ($2,600.00) |
CO#4 76072 Credit for detention hardware | 09/10/2021 | |
Amendment | ($12,480.00) |
CO#5 76155 Credit for steel mounting plates not required due to restart chairs having integral plate | 09/17/2021 | |
Amendment | $2,065.00 |
CO# 7 76675 Exterior gate keying | 03/08/2022 | |
Amendment | $8,547.00 |
CO# 76873 Steel angle replacement | 03/14/2022 | |
Amendment | $25,025.00 |
CO #8 76908 detention key changes | 03/28/2022 | |
Amendment | $2,494.00 |
CO# 9 769011 revise steel angle attachment to building 8 interview rooms ceiling | 04/21/2022 | |
Amendment | $26,007.00 |
CO #11 77071 security access doors | 05/25/2022 | |
Amendment | $15,728.00 |
CO#13 76982 Additional door hardware and ceiling access panels | 06/03/2022 | |
Amendment | $38,379.00 |
CO#14 76951 Ceiling security access revisions | 06/27/2022 | |
Amendment | $12,393.00 |
CO#17 76972 Install temporary chain link fence | 07/08/2022 | |
Amendment | $40,000.00 |
CO #15 76949 Revised milestone completion date | 07/18/2022 | |
Amendment | $9,588.00 |
CO#18 77191 Canopy woven rod bracing | 07/22/2022 | |
Amendment | $10,000.00 |
CO#16 77273 Punch list work | 08/03/2022 | |
Amendment | ($3,124.00) |
CO #21 76949A final credit | 08/12/2022 | |
Amendment | $17,682.00 |
CO 20 77180 Install temporary panels for electrical junction boxes | 08/29/2022 | |
Amendment | $315.00 |
CO #23 77273A Removal & replacement of ceiling tile for sprinkler system | 10/17/2022 | |
Amendment | $17,296.00 |
01/31/2023 | CO#24 77545 increase & extension to correct elevator code violations Upstate CF Franklin County | 12/13/2022 |
Amendment | $155,975.00 |
CO#25 77944 Provide security glazing at basement & 2nd floor classroom lighing | 01/30/2023 | |
Amendment | $0.00 |
06/02/2023 | CO# 26 78512 No cost time extension | 03/29/2023 |
Amendment | $1,292,161.00 |
06/01/2024 | Revisions of control consoles steel doors frames hardware & time extension | 03/04/2024 |