Vendor Name: M & J ELECTRICAL CONTRACTORS CORP
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44972C
Current Contract Amount: $2,213,394.00
Spending to Date: $1,990,666.09
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,675,000.00 |
11/07/2019 | 01/28/2022 | Rehab Inmate Showers Bldg 84 & 93 Phase 1 Taconic CF Westchester County | 11/07/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $41,301.00 |
CO#2 75091 change specifications for hardware and door vision panels | 11/05/2020 | |
Amendment | $69,510.00 |
CO#3 75093 Wall assembly | 11/23/2020 | |
Amendment | $0.00 |
04/17/2022 | Change order #6 75291 no cost time extension | 02/10/2021 |
Amendment | $20,599.00 |
Change order #7 75766 recess concrete slab for ADA shower receptors Bldg 93 East & Bldg 84 | 05/21/2021 | |
Amendment | $57,295.00 |
CO#5 75477 Rehabilitate inmate showers building 84 & 93 phase I | 05/28/2021 | |
Amendment | $63,972.00 |
CO#4 75094 Rehabilitate inmate showers bldg 84 & 93 phase 1 | 06/03/2021 | |
Amendment | $1,647.00 |
CO #8 75805 increase to change shower partitions | 06/10/2021 | |
Amendment | $117,049.00 |
CO#9 75766 Shower rehab floors & walls | 07/02/2021 | |
Amendment | $0.00 |
10/04/2022 | CO # 10 76264 No cost time extension | 08/06/2021 |
Amendment | $2,161.00 |
CO#11 77211 Delay claim November 7 2019 through December 31 2021 | 06/23/2022 | |
Amendment | $0.00 |
01/06/2023 | CO#12 77559 No cost time extension | 07/29/2022 |
Amendment | $23,621.00 |
CO#14 77498 Pitch to drain in Building 93 | 11/10/2022 | |
Amendment | $28,727.00 |
01/07/2023 | CO #13 77658 extend and add floor slope | 11/16/2022 |
Amendment | ($706.00) |
01/08/2023 | CO#15 77659 Time extension & Credit removal of wall | 11/30/2022 |
Amendment | $11,446.00 |
CO 16 77821 Bar joist reinforcement | 12/09/2022 | |
Amendment | $21,333.00 |
CO 17 77904 Reinforcement deteriorated bar joist | 02/09/2023 | |
Amendment | $0.00 |
12/12/2023 | CO#18 78571 no cost time extension | 04/10/2023 |
Amendment | $10,138.00 |
CO#19 78960 additional slab in fill for shower rooms 1 13 & 1 18 | 10/30/2023 | |
Amendment | $23,583.00 |
CO#20 79345 Restoration to cells G22 & J82 in bldg 84 | 02/01/2024 | |
Amendment | $46,718.00 |
CO# 21 79448 Increase to provide slope to floor drain | 03/04/2024 |