Vendor Name: S & O CONSTRUCTION SERVICES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D44972P
Current Contract Amount: $796,162.00
Spending to Date: $661,204.91
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $696,111.00 |
11/07/2019 | 01/28/2022 | Rehab Inmate Showers Bldg 84 & 93 Phase 1 Taconic CF Westchester County | 11/07/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
04/17/2022 | Change order #1 75349 no cost time extension | 01/12/2021 |
Amendment | $0.00 |
10/04/2022 | CO # 2 76267 No cost time extension | 08/06/2021 |
Amendment | $1,348.00 |
CO#3 77262 Floor drain investigation. | 07/15/2022 | |
Amendment | $0.00 |
01/06/2023 | CO#4 77589 no cost time extension | 08/30/2022 |
Amendment | $0.00 |
12/04/2023 | CO#5 78574 no cost time extension | 04/10/2023 |
Amendment | $3,896.00 |
CO#6 78763 Reimburses contractor for lost time | 06/14/2023 | |
Amendment | $63,414.00 |
CO#7 78582 Filtering for domestic hot water service | 09/21/2023 | |
Amendment | $3,326.00 |
CO#9 79152 Replace shower drains | 11/16/2023 | |
Amendment | $21,788.00 |
CO#8 79052 Replace cartridges & shower controls | 12/08/2023 | |
Amendment | $6,279.00 |
07/29/2024 | CO#10 79848 Drain removal | 04/17/2024 |