Vendor Name: LANCASTER DEVELOPMENT & TULLY CONSTRUCTION CO LLC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263945
Current Contract Amount: $26,444,027.33
Spending to Date: $26,444,027.33
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $28,852,932.84 |
08/27/2019 | 04/30/2021 | New Bridge & Highway Reconstruction Taconic State Parkway Pudding Street Interchange Putnam County | 08/27/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $3,283.57 |
CO#4 - New item | 03/10/2020 | |
Amendment | $0.00 |
09/02/2021 | CO#5 NCTE | 06/02/2020 |
Amendment | $4,224.73 |
CO#8 Winter Pavement Patch | 07/30/2020 | |
Amendment | $4,909.55 |
CO#9 Provide Vacuum Service | 08/21/2020 | |
Amendment | $2,133.32 |
Change order #16 emergency work for sandbags to protect median | 02/12/2021 | |
Amendment | $12,963.16 |
Change order #19 new earthwork and traffic control items | 06/24/2021 | |
Amendment | $0.00 |
10/01/2021 | CO# 21 No cost time extension | 10/06/2021 |
Amendment | $0.00 |
11/20/2021 | CO# 23 No cost time extension | 10/28/2021 |
Amendment | $33,001.15 |
CO # 24 Additional materials for contract work | 11/29/2021 | |
Amendment | $17,269.22 |
CO#26 New items | 01/14/2022 | |
Amendment | $96,803.00 |
CO#28 Additional guide rail & environmental work | 03/21/2022 | |
Amendment | ($2,656,042.68) |
CO#29 Item decreases | 09/09/2022 | |
Amendment | ($14,569.20) |
CO#30 Pavement and longitudinal joint quality adjustments | 11/17/2022 |