Vendor Name: S & O CONSTRUCTION SERVICES INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45161H
Current Contract Amount: $1,320,178.00
Spending to Date: $1,295,230.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,170,886.00 |
05/22/2019 | 05/13/2020 | Replace Heating System Bldg 19 Bedford Hill CF Westchester County | 05/22/2019 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($4,139.00) |
12/09/2020 | Change Order#1 74342 Adding time & modifies precast trench and piping | 03/05/2020 |
Amendment | $0.00 |
05/21/2021 | CO#2 75353 No cost time extension | 11/23/2020 |
Amendment | $86,902.00 |
Change order #3 75347 new items curb trench fence gate walkway modifications | 06/04/2021 | |
Amendment | $0.00 |
12/13/2021 | CO#5 76075 No cost time extention | 07/30/2021 |
Amendment | $0.00 |
01/25/2022 | CO# 6 77113 No cost time extension | 04/12/2022 |
Amendment | $0.00 |
12/31/2022 | CO#8, No-cost time extension | 10/11/2022 |
Amendment | $27,786.00 |
CO#7 77469 gauge galvanized steel plates | 10/24/2022 | |
Amendment | $17,966.00 |
CO#9 78013 recirculating pumps | 01/19/2023 | |
Amendment | $20,777.00 |
CO#11 78789 Increase in supplies & labor | 09/19/2023 | |
Amendment | $0.00 |
10/09/2023 | CO#13 79309 No cost time extension | 11/01/2023 |
Amendment | $0.00 |
02/23/2024 | CO# 14 78789A No cost time extension | 03/04/2024 |