Vendor Name: A COLARUSSO & SON INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263769
Current Contract Amount: $6,106,406.21
Spending to Date: $6,106,406.21
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $5,232,969.00 |
07/20/2018 | 05/22/2019 | Empire State Trail Construction Rte 299 Hudson Valley to Wallkill Valley Rail Trail Ulster County | 07/20/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $130,265.93 |
CO#1 New Utilities item | 11/09/2018 | |
Amendment | $271,449.70 |
CO# 5 New Items 203.03 620.02 623.12 950.1801 & Increases | 02/06/2019 | |
Amendment | $71,341.01 |
CO#6 Add New Items | 03/04/2019 | |
Amendment | $188,308.34 |
CO#7 New Items | 03/26/2019 | |
Amendment | $459,874.94 |
CO#8 Item Increases & New Items | 04/22/2019 | |
Amendment | $0.00 |
07/31/2019 | CO#9 Materials Related NCTE | 06/10/2019 |
Amendment | ($308.93) |
Add New Items Concrete for Structures Bar Reinforcement Protective Seal & Item Increases & Decreases | 06/28/2019 | |
Amendment | ($16,601.40) |
CO#12 Item increases and decreases | 07/31/2019 | |
Amendment | ($965.67) |
CO#11 New & Increased Item Quantities Hudson Valley Rail Trail | 09/10/2019 | |
Amendment | ($78.30) |
CO#13 New Items Empire State Trail Construction | 10/02/2019 | |
Amendment | ($12,494.42) |
CO#15 Cleanup | 10/23/2019 | |
Amendment | ($3,108.70) |
CO#15 New Items Rail Trail | 11/15/2019 | |
Amendment | ($141,732.50) |
CO#16 Renegotiate Major Items | 12/06/2019 | |
Amendment | ($73,177.82) |
CO#17 New Increased and Decreased Items Rail Trail | 02/05/2020 | |
Amendment | $665.03 |
CO#18 Cleanup | 08/17/2020 |