Vendor Name: ECCO III ENTERPRISES INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263687
Current Contract Amount: $11,407,637.44
Spending to Date: $11,407,637.44
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $7,688,000.00 |
07/12/2018 | 07/01/2019 | Lower Hudson Transit Link NY-59 Pedestrian Safety Improvements Rockland County | 07/12/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($62.00) |
CO#1 Modify Pavement Restoration Along Curbs | 11/30/2018 | |
Amendment | $0.00 |
07/29/2019 | CO #3 NCTE | 01/10/2019 |
Amendment | $8,765.47 |
CO 2 New item | 03/26/2019 | |
Amendment | $685,400.96 |
CO#5 New Bridge Rails | 05/13/2019 | |
Amendment | $346,765.50 |
CO#8 Temporary Plastic Barrier Fence | 05/30/2019 | |
Amendment | $0.00 |
04/02/2020 | CO#10 NCTE | 08/01/2019 |
Amendment | $973,025.28 |
CO#6 New Item Temporary Pedestrian Safety Provisions | 11/18/2019 | |
Amendment | $138,589.68 |
CO#9 New Drainage Items | 01/08/2020 | |
Amendment | $0.00 |
09/08/2020 | CO#14 NCTE | 03/25/2020 |
Amendment | $156,179.74 |
CO#12 New Items Drainage System Re-Design | 07/27/2020 | |
Amendment | $0.00 |
11/25/2020 | CO#17 NCTE | 09/23/2020 |
Amendment | $75,676.31 |
CO #13 New items and decreases | 10/29/2020 | |
Amendment | $102,675.00 |
CO#16 Cast in place curb item overrun | 11/19/2020 | |
Amendment | $104.32 |
CO#21 Additional funds to account for field conditions and overruns | 02/25/2022 | |
Amendment | $846,760.37 |
CO#23 New items extended overhead supervision | 09/07/2022 | |
Amendment | $463,341.76 |
CO #22 new items | 09/21/2022 | |
Amendment | ($77,491.09) |
CO#24 Item decreases | 06/08/2023 |