Vendor Name: RIFENBURG CONSTRUCTION INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263603
Current Contract Amount: $5,719,439.82
Spending to Date: $5,719,439.82
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $5,795,562.00 |
05/11/2018 | 12/31/2019 | Comm Vehicle Inspection&Hwy Safety Ops Facility I-87 T/O Champlain Clinton CO (Site Construction) | 05/11/2018 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $5,670.50 |
CO#1 NYS Commercial Vehicle Inspection Facility Clinton County | 09/06/2018 | |
Amendment | $47,753.81 |
CO#4 Extra Asbestos Work | 10/25/2018 | |
Amendment | $59,996.00 |
CO#3 Items Increased for Sewer Line | 12/10/2018 | |
Amendment | $32,651.85 |
CO#2 Waterlines Installation & Hydrant Adjustments | 01/18/2019 | |
Amendment | $24,030.50 |
CO #5 Item increase and new items | 02/04/2019 | |
Amendment | $84,917.53 |
CO#6 New Items Commercial Vehicle Inspection & Hwy. Safety Operations | 05/01/2019 | |
Amendment | $15,702.78 |
CO#8 Grinder Pumps & Box Beam Guiderail Items Added | 06/21/2019 | |
Amendment | $34,009.07 |
CO#10 New & Increased Items Excavation Waterproofing & Structural Work | 12/06/2019 | |
Amendment | $6,257.56 |
CO#9 New Dumpster Pad & Fencing | 12/24/2019 | |
Amendment | $41,342.53 |
CO#11 New Increased & Decreased Items Utility Changes | 02/03/2020 | |
Amendment | $0.00 |
01/31/2020 | CO#14 NCTE | 02/19/2020 |
Amendment | $0.00 |
02/29/2020 | CO#15 NCTE | 04/21/2020 |
Amendment | $45,968.36 |
03/31/2020 | CO#12 New Increased & Decreased Concrete Item Quantities | 05/14/2020 |
Amendment | $38,378.95 |
CO16# Trench & Culvert Price Adjustment | 05/28/2020 | |
Amendment | ($528,778.11) |
CO#13 Cleanup | 07/17/2020 | |
Amendment | $15,976.49 |
CO#17 Final Fuel & Asphalt Adjustment | 08/28/2020 |