Vendor Name: POWER & CONSTRUCTION GROUP INC
Agency Name: Transportation, Department of
Department/Facility Name: Department of Transportation
Contract Number: D263544
Current Contract Amount: $2,017,783.65
Spending to Date: $1,974,894.22
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $1,841,972.60 |
11/03/2017 | 10/31/2019 | Regional Traffic Signal Project, Onondaga, Cortland, Region 3 | 11/03/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $0.00 |
06/30/2020 | CO#2 NCTE | 11/15/2019 |
Amendment | $24,600.00 |
CO#3 New Item Traffic Signals | 04/20/2020 | |
Amendment | $90,485.80 |
CO#4 New & Increased Traffic Signal Items | 06/24/2020 | |
Amendment | $0.00 |
11/20/2020 | CO#5 NCTE | 07/06/2020 |
Amendment | $50,308.13 |
CO#8 - New items | 08/24/2020 | |
Amendment | $28,281.64 |
Change order #6 increase & decreases | 09/18/2020 | |
Amendment | $0.00 |
06/30/2021 | Change order #9 no cost time extension | 11/27/2020 |
Amendment | $7,209.64 |
CO#7 Added work traffic signal project | 12/10/2020 | |
Amendment | $3,319.43 |
CO#10 New items rock drill signal pole foundations | 07/19/2021 | |
Amendment | $0.00 |
09/30/2021 | CO#12 No cost time extension | 08/06/2021 |
Amendment | $713.63 |
CO#11 Decreases & traffic signals | 08/31/2021 | |
Amendment | $19,413.49 |
CO#14 new items traffic signal installations | 02/15/2023 | |
Amendment | ($48,520.71) |
CO #13 Clean up change order | 04/02/2024 |