Vendor Name: OAKGROVE CONSTRUCTION INC
Authority Name: Thruway Authority
Department/Facility Name: New York State Thruway Authority
Contract Number: D214545
Current Contract Amount: $57,536,068.04
Spending to Date: $0.00
Contract Type: Construction - Highway
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $66,474,997.50 |
11/06/2017 | 10/15/2019 | Reconstruct/Rehab I-90 Pvmnt, Replace 1 Bridge over Norfolk S. RR, Rehab 4 Bridges, Buffalo Division | 11/06/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($128,912.00) |
CO#2, Item increased and decreases. | 05/04/2018 | |
Amendment | $17,017.05 |
CO 3 Added paving and oil pipeline conflict | 05/30/2019 | |
Amendment | $7,402.11 |
CO#4 Guide rail removal and utility conflict | 05/31/2019 | |
Amendment | $22,932.43 |
CO#5 Bridge joint repairs. | 05/31/2019 | |
Amendment | ($371,039.64) |
CO#7 New Item Value Engineering Cost Proposal Construction Savings & Decrease 3 items | 04/20/2020 | |
Amendment | ($8,486,329.41) |
CO#1 final | 05/07/2020 |