Vendor Name: OCONNELL ELECTRIC COMPANY INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D42378E
Current Contract Amount: $16,798,399.00
Spending to Date: $16,488,991.00
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $12,987,100.00 |
06/05/2017 | 09/25/2019 | Upgrade Electric Distribution System Willard Drug Treatment Center Seneca County | 06/05/2017 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $131,895.00 |
CO#1 71772 Change manhole Upgrade Electric Distribution System Willard Drug Treatment Ctr Seneca Co | 04/19/2018 | |
Amendment | $228,802.00 |
CO#2 72065 Split Bus Switchgear & Temporary Generator Connection Box & New Spec 261313 | 06/06/2018 | |
Amendment | ($83,581.00) |
CO# 4 72803 Credit for Bollards & Adds Misc Obstructions & Meter Bollards | 11/20/2018 | |
Amendment | $90,765.00 |
CO#3 72605 NYSEG Required Line Voltage Meter Section | 12/21/2018 | |
Amendment | ($35,368.00) |
CO #5 73020 Credit for temp generator and temp power. | 01/07/2019 | |
Amendment | $2,309,700.00 |
CO #6 73133 Increase Specific Allowance Additional NYSEG Substation Costs | 03/26/2019 | |
Amendment | $41,477.00 |
CO#7 73298 Willard Drug Treatment Center Upgrade Electrical | 04/09/2019 | |
Amendment | $0.00 |
12/23/2020 | CO#8 73900 NCTE | 08/09/2019 |
Amendment | $137,139.00 |
CO#9 74205 Provide Extended Equipment Warranties | 05/29/2020 | |
Amendment | $19,477.00 |
CO#11 74682 Delay Claim due to NYSEG delay to complete Substation upgrades | 06/22/2020 | |
Amendment | $31,826.00 |
CO#13 74745 Delay Claim Sept & Oct 2019 due to NYSEG Delay To Complete Substation | 06/30/2020 | |
Amendment | $18,563.00 |
CO#12 74711 Delay Claim for August 2019 due to NYSEG Delay To Complete Substation | 06/30/2020 | |
Amendment | $35,270.00 |
CO#14 74796 Delay Claim for Nov & Dec 2019 due to NYSEG Delay To Complete Substation | 06/30/2020 | |
Amendment | $406,729.00 |
CO#10 74581 Upgrade Electric Distribution System | 07/10/2020 | |
Amendment | $0.00 |
03/09/2021 | CO#15 75031 NCTE | 08/24/2020 |
Amendment | $0.00 |
08/03/2021 | CO#17 75250 No cost time extension | 11/18/2020 |
Amendment | $19,267.00 |
Change order #18 75636 Delay claim June 5 2017 through June 30 2020 | 06/02/2021 | |
Amendment | $80,142.00 |
CO#16 75233 Delay claim | 10/19/2021 | |
Amendment | $203,768.00 |
CO#19 76167 Reimbursement of cost due to delays at Willard Drug Treatment Center | 11/29/2021 | |
Amendment | $44,127.00 |
CO#20 73133A Amend cost for additional NYSEG sub station | 01/21/2022 | |
Amendment | $131,301.00 |
CO# 21 76730 Delay claim | 07/08/2022 |