Vendor Name: BUNKOFF GENERAL CONTRACTORS INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45139C
Current Contract Amount: $2,463,624.00
Spending to Date: $2,398,974.00
Contract Type: Construction - Miscellaneous
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $2,301,000.00 |
12/29/2016 | 12/21/2018 | Replace main substation, banks A,B,C, State Office Campus, Albany (C) | 12/29/2016 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | ($5,654.00) |
12/21/2018 | Banks A, B & C Replacement Main Substation State PB Campus | 03/16/2017 |
Amendment | ($3,355.00) |
12/21/2018 | CO#2, 71359, replace main substation, banks A,B,C, State Office Campus, Albany | 07/05/2017 |
Amendment | $33,216.00 |
CO#3, Shoring, replace main substation, banks A,B,C, State Campus, Albany (C) | 10/25/2017 | |
Amendment | $39,925.00 |
CO#4 71808 Replace Main Substation, Banks A,B & C, State Office Campus, Albany County | 11/30/2017 | |
Amendment | $102,484.00 |
CO#5 71918 Replace Main Substation Banks A,B,C State Office Campus, Albany County | 02/07/2018 | |
Amendment | $0.00 |
02/12/2020 | CO#6 73086 NCTE | 01/11/2019 |
Amendment | $0.00 |
12/03/2020 | Change order #7 74676 No Cost Time Extension | 04/14/2020 |
Amendment | ($3,992.00) |
CO#8 74732 Credit for relocation of sump pit | 05/29/2020 | |
Amendment | $0.00 |
01/21/2021 | CO#9 75648 no cost time extension | 02/24/2021 |