Vendor Name: OCONNELL ELECTRIC COMPANY INC
Agency Name: General Services, Office of
Department/Facility Name: Office of General Services - Design & Construction
Contract Number: D45139E
Current Contract Amount: $14,608,548.00
Spending to Date: $14,483,605.67
Contract Type: Construction - Building
Contract Information
Contract Amendment Information
Transaction Type | Transaction Amount | Contract Start Date | Contract End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|---|
Original Contract | $11,477,400.00 |
12/29/2016 | 12/21/2018 | Replace main substation, banks A,B,C, State Office Campus, Albany (E) | 12/29/2016 |
Transaction Type | Transaction Amount | Amended End Date | Description | Transaction Approved/Filed Date |
---|---|---|---|---|
Amendment | $9,315.00 |
CO 1 #71613 Transformer Weld testing Banks A, B &C Replacement Main substation State OB | 08/29/2017 | |
Amendment | $49,456.00 |
CO 2 #71509 Banks A,B,& C Replacement, Main Substation State OB Campus | 09/19/2017 | |
Amendment | $42,860.00 |
CO#3 71920 Banks A, B & C Replacement, Main Substation State OB Campus | 01/11/2018 | |
Amendment | $22,874.00 |
CO#4 71924 Banks A B & C Replacemt,electrical changes Main Substation State OB Campus | 01/18/2018 | |
Amendment | $154,469.00 |
CO#5 72343 Thermal Monitoring on Switch gear Banks A, B & C Replacement | 06/01/2018 | |
Amendment | $330,626.00 |
CO#6 72469 Increase Allowance for Work Performed by Utility | 07/10/2018 | |
Amendment | $117,596.00 |
CO#7 72662 Bay 12 Switches | 09/27/2018 | |
Amendment | $36,594.00 |
CO#9 72996 Remove Remote Operator | 12/10/2018 | |
Amendment | $55,014.00 |
CO#8 72997 Provide HMI for SBS Software and Provide SCADA points for 2 Chargers | 01/02/2019 | |
Amendment | $0.00 |
04/30/2019 | CO # 11 73329 NCTE | 02/28/2019 |
Amendment | $7,416.00 |
CO#10 73248 Emergency Feed to D Gear & Wall Mount CCTV Monitor | 03/06/2019 | |
Amendment | $29,402.00 |
CO#73574 Relocate switch gear. | 05/21/2019 | |
Amendment | $0.00 |
01/20/2020 | CO#13 73706 NCTE | 06/10/2019 |
Amendment | $40,477.00 |
CO# 14 73675 Separation of SUNY feeders associated to C gear. | 06/28/2019 | |
Amendment | $71,634.00 |
CO#16 73746 Relocation of power feeders | 08/05/2019 | |
Amendment | $31,737.00 |
CO#15 73742 SCADA System Changes for WEAM System | 08/27/2019 | |
Amendment | $19,265.00 |
CO#17 74106 Provide T Bodies For 350 Cables & Work To D Gear Transfer Switch | 11/19/2019 | |
Amendment | $0.00 |
02/10/2021 | Change Order #20 74658 No Cost Time Extension | 04/15/2020 |
Amendment | $24,183.00 |
CO#18 74480 Banks A B C Replacement Main Substation | 04/24/2020 | |
Amendment | $143,720.00 |
CO#19 74479 Transformer Connection Upgrade | 05/12/2020 | |
Amendment | $12,741.00 |
CO#21 74781 Credit For Ductbanks & Provide Conduits & Control Wiring | 08/14/2020 | |
Amendment | $322,037.00 |
CO#22 74807 Design Error | 08/28/2020 | |
Amendment | $27,262.00 |
03/14/2021 | CO#23 75036 TE & Additional funding to maintain 2 existing feeds to Bldg 12 | 10/13/2020 |
Amendment | $12,656.00 |
CO #24 75035 Relay re-setting | 10/20/2020 | |
Amendment | $21,504.00 |
03/29/2021 | CO#25 75331 provide for closed transition when switching outdoor Switchgear D | 02/10/2021 |
Amendment | $99,932.00 |
04/23/2021 | CO# 29 75672 increase & extend for for parallel testing | 06/08/2021 |
Amendment | $96,973.00 |
08/16/2021 | Change order #29 control #75672 additional time and work | 06/25/2021 |
Amendment | $0.00 |
11/22/2021 | Change order #30 control #75672A 98 day extension | 08/26/2021 |
Amendment | $1,351,405.00 |
CO#31 77287 Delay claim | 06/29/2022 |