Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY - Upstate Medical University | D550346 |
$3,035,000.00
|
$3,035,000.00 |
03/15/2022 | 08/01/2024 | Treatment unit renovations at the Hutchings Psychiatric Center | Construction - Building | 12/29/2022 |
SUNY at Buffalo | D000020 |
$651,701.00
|
$641,421.00 |
12/01/2021 | 08/08/2023 | Boiler replacement in Ellicott Complex | Construction - Miscellaneous | 12/22/2021 |
SUNY at Buffalo | D000019 |
$1,724,021.00
|
$0.00 |
12/01/2021 | 08/12/2023 | Electrical upgrades in Ellicott Complex at SUNY Buffalo | Construction - Miscellaneous | 12/10/2021 |
SUNY at Buffalo | D000016 |
$3,171,785.00
|
$3,021,105.00 |
09/01/2021 | 06/30/2024 | Replacement of curtainwall system for Goodyear Hall at SUNY Buffalo | Construction - Miscellaneous | 08/26/2021 |
SUNY at Buffalo | D000036 |
$4,021,692.00
|
$1,000,000.00 |
05/20/2023 | 08/08/2023 | Roof replacement (phase 2) of Richmond and Wilkeson Quads in Ellicott Complex | Construction - Miscellaneous | 01/23/2023 |
SUNY at Buffalo | D000037 |
$4,000,000.00
|
$3,000,000.00 |
05/01/2023 | 08/15/2024 | Construction of residential welcome center at Fargo Quad in Ellicott Complex | Construction - Miscellaneous | 01/27/2023 |
SUNY at Buffalo | D000018 |
$2,365,324.00
|
$1,774,838.00 |
11/01/2021 | 02/08/2023 | Roof replacement for Spaulding Quad | Construction - Miscellaneous | 11/10/2021 |
SUNY at Buffalo | D000043 |
$270,000.00
|
$70,000.00 |
01/09/2023 | 08/08/2024 | Design for offices and entrances at Fargo and Wilkeson Quads in Ellicott Complex | Construction - Miscellaneous | 04/07/2023 |
SUNY at Buffalo | D000044 |
$714,880.00
|
$50,000.00 |
01/05/2023 | 08/13/2025 | Roof repair of Ellicott Complex terrace and replace pavers for Evans and Fargo Quads (phase 1) | Construction - Miscellaneous | 04/04/2023 |
SUNY at Buffalo | D000032 |
$2,739,025.00
|
$2,257,176.00 |
12/15/2022 | 08/08/2025 | Renovation of first floor lounge at Richmond Quad | Construction - Miscellaneous | 09/27/2022 |
SUNY at Buffalo | D000030 |
$1,650,179.00
|
$425,000.00 |
05/23/2023 | 08/08/2024 | Electrical upgrades phase 4 for Fargo Quad | Construction - Miscellaneous | 08/18/2022 |
SUNY at Buffalo | D000033 |
$1,316,925.00
|
$1,175,000.00 |
02/01/2023 | 08/13/2024 | Bathroom renovations at Goodyear Hall | Construction - Miscellaneous | 12/22/2022 |
SUNY at Buffalo | D000035 |
$595,675.00
|
$200,000.00 |
05/20/2023 | 08/08/2024 | Reroofing and lightning protection at Goodyear Hall | Construction - Miscellaneous | 12/22/2022 |
SUNY at Buffalo | D000027 |
$5,167,360.00
|
$4,962,088.00 |
03/08/2022 | 08/15/2024 | Phase 1 upgrades to Clement Hall | Construction - Miscellaneous | 03/30/2022 |
SUNY at Buffalo | D000015 |
$887,043.00
|
$730,000.00 |
05/20/2021 | 06/30/2024 | Replacement of floor heaters in Governors Residence Halls | Construction - Miscellaneous | 06/16/2021 |
College of Technology at Alfred | D220001 |
$365,000.00
|
$0.00 |
01/18/2023 | 08/31/2023 | Standby transfer switches installation at Robinson/Champlain and Getman Halls | Construction - Miscellaneous | 01/31/2023 |
SUNY at Albany | D220105 |
$6,402,094.00
|
$5,595,479.00 |
01/25/2023 | 10/13/2023 | Abatement and replacement of ceilings and floors at University at Albany's uptown residence halls | Construction - Miscellaneous | 03/02/2023 |
SUNY at Albany | D220012 |
$5,076,070.00
|
$5,073,413.00 |
05/01/2022 | 12/31/2022 | Abatement and floor/ceiling replacement in Clinton, Delancey and Morris Halls of Colonial Quad | Construction - Miscellaneous | 07/22/2022 |
SUNY at Albany | D220135 |
$1,525,000.00
|
$1,400,000.00 |
04/03/2023 | 08/04/2025 | Renovation of Ten Eyck Hall | Construction - Miscellaneous | 04/07/2023 |
SUNY at Albany | D210049 |
$16,480,046.00
|
$16,325,000.00 |
06/01/2022 | 06/30/2024 | Renovation of Paine and Zenger Halls, University at Albany | Construction - Miscellaneous | 01/13/2022 |
College at Oneonta | D990575 |
$1,190,167.00
|
$0.00 |
01/11/2023 | 11/30/2024 | Upgrade to IT infrastructure in Blodgett Hall | Construction - Miscellaneous | 01/18/2023 |
College of Technology at Delhi | D000394 |
$170,000.00
|
$110,000.00 |
01/20/2023 | 12/31/2024 | Masonry repair at Gerry and Dubois Halls | Construction - Miscellaneous | 02/24/2023 |
College of Technology at Delhi | D000393 |
$918,000.00
|
$900,000.00 |
05/20/2022 | 08/15/2022 | Fire alarm system replacement in Murphy and O'Connor Halls | Construction - Miscellaneous | 04/06/2022 |
College of Technology at Delhi | D000395 |
$112,500.00
|
$75,000.00 |
02/01/2023 | 08/31/2025 | Replacement of fire alarm system in Catskill Hall | Construction - Miscellaneous | 02/23/2023 |
College at New Paltz | D991451 |
$5,562,500.00
|
$920,000.00 |
01/30/2023 | 07/23/2023 | Renovation of restrooms and fire protection systems in Bliss Hall | Construction - Miscellaneous | 07/20/2022 |
College at New Paltz | D991452 |
$1,168,685.00
|
$25,000.00 |
11/01/2022 | 08/01/2023 | Basement condensation at Ridgeview Hall | Construction - Miscellaneous | 06/27/2022 |
College at New Paltz | D991450 |
$1,304,118.00
|
$805,000.00 |
01/02/2023 | 10/22/2024 | Replacement of the Bliss and Gage four stop elevators | Construction - Miscellaneous | 07/20/2022 |
Office of Children & Family Services | D070986 |
$950,000.00
|
$0.00 |
10/30/2023 | 10/29/2028 | Project management agreement including third party procurements Statewide | Consultant - Construction Related Services | 01/12/2024 |
College at Cortland | T100712 |
$878,900.00
|
$872,000.00 |
07/10/2017 | 08/31/2021 | CASEY SMITH FEASIBILITY STUDY- | Contracts Not Subject to OSC Pre-Audit | 07/18/2019 |
College at Cortland | T000844 |
$1,200,000.00
|
$500,000.00 |
08/01/2022 | 12/31/2024 | ALGER HALL RENOVATIONS DESIGN | Contracts Not Subject to OSC Pre-Audit | 08/01/2022 |
SUNY at Buffalo | T50103A |
$1,100,000.00
|
$0.00 |
11/01/2019 | 09/30/2020 | GOVERNORS ROOF REHABILITATION | Contracts Not Subject to OSC Pre-Audit | 11/07/2019 |
SUNY at Buffalo | T300063 |
$635,162.00
|
$635,162.00 |
04/15/2020 | 12/01/2022 | DESIGN FOR SPAULDING ROOF REPL | Contracts Not Subject to OSC Pre-Audit | 04/23/2021 |
SUNY at Buffalo | T300064 |
$188,579.00
|
$188,579.00 |
04/15/2020 | 12/01/2022 | DESIGN FOR ELLICOTT COMPLEX BO | Contracts Not Subject to OSC Pre-Audit | 04/23/2021 |
SUNY at Buffalo | T300065 |
$517,912.00
|
$517,912.00 |
07/06/2021 | 01/05/2023 | CLEMENT HOSPITALITY REHAB | Contracts Not Subject to OSC Pre-Audit | 07/21/2021 |
SUNY at Buffalo | T300061 |
$80,000.00
|
$20,000.00 |
04/01/2021 | 08/01/2022 | ELLICOTT BOILER FEASIBILITY ST | Contracts Not Subject to OSC Pre-Audit | 03/12/2021 |
SUNY at Buffalo | T300078 |
$350,000.00
|
$350,000.00 |
07/05/2022 | 08/15/2023 | GOODYEAR HALL TOILET ROOM UPGR | Contracts Not Subject to OSC Pre-Audit | 07/05/2022 |
SUNY at Buffalo | T300076 |
$467,824.00
|
$467,824.00 |
04/01/2022 | 08/08/2025 | RICHMOND QUAD FIRST FLOOR REHA | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300060 |
$550,755.00
|
$550,755.00 |
04/01/2020 | 08/13/2022 | RICHMOND ELECTRICAL DESIGN PRO | Contracts Not Subject to OSC Pre-Audit | 11/25/2020 |
SUNY at Buffalo | T300086 |
$20,000.00
|
$15,000.00 |
03/01/2023 | 05/01/2023 | FEASIBILITY STUDY FOR RESIDENC | Contracts Not Subject to OSC Pre-Audit | 03/06/2023 |
SUNY at Buffalo | T300085 |
$270,000.00
|
$0.00 |
01/09/2023 | 08/08/2024 | FARGO AND WILKESON RENOVATION | Contracts Not Subject to OSC Pre-Audit | 03/03/2023 |
SUNY at Buffalo | T300074 |
$300,000.00
|
$255,000.00 |
04/01/2022 | 08/08/2025 | GOODYEAR HALL RE-ROOFING | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300071 |
$300,000.00
|
$165,000.00 |
04/01/2022 | 08/08/2024 | ELLICOTT BOILER REPLACEMENT - | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300075 |
$500,000.00
|
$470,000.00 |
04/01/2022 | 08/08/2024 | RICHMOND & RED JACKET ROOFING | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300072 |
$400,000.00
|
$395,000.00 |
04/01/2022 | 08/08/2024 | GOVERNORS COMPLEX WINDOW HEATE | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300073 |
$231,383.00
|
$192,000.00 |
04/01/2022 | 08/13/2025 | SPAULDING QUAD MAIN LOUNGE REH | Contracts Not Subject to OSC Pre-Audit | 03/17/2022 |
SUNY at Buffalo | T300068 |
$442,564.00
|
$375,000.00 |
11/08/2021 | 08/08/2023 | CONSULTING FOR CONSTRUCTION RE | Contracts Not Subject to OSC Pre-Audit | 12/02/2021 |
SUNY at Buffalo | T500125 |
$493,896.00
|
$493,895.00 |
06/26/2019 | 06/30/2022 | DESIGN FOR REPLACEMENT OF GOOD | Contracts Not Subject to OSC Pre-Audit | 07/18/2019 |
SUNY at Buffalo | T300066 |
$355,707.00
|
$355,000.00 |
11/01/2021 | 08/08/2024 | FARGO ELECTRICAL PHASE 4 | Contracts Not Subject to OSC Pre-Audit | 10/18/2021 |
SUNY at Buffalo | T50148A |
$120,000.00
|
$120,000.00 |
08/03/2020 | 06/30/2024 | DESIGN & CONSTRUCTION FOR GOVE | Contracts Not Subject to OSC Pre-Audit | 11/11/2020 |
SUNY at Buffalo | T300083 |
$270,000.00
|
$105,000.00 |
01/09/2023 | 08/08/2024 | RENOVATE EVANS STAFF APT. | Contracts Not Subject to OSC Pre-Audit | 01/10/2023 |