Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Department of Transportation | D262401 |
$2,112,452.71
|
$2,112,452.71 |
01/15/2014 | 07/31/2015 | REPAIR & REPLACEMENT CULVERTS ALBANY ESSEX & WARREN COUNTIES | Construction - Highway | 01/15/2014 |
Department of Transportation | D262547 |
$874,465.66
|
$874,465.66 |
03/12/2014 | 08/31/2014 | SLOPE REPAIR ROUTE 2 TOWN OF PETERSBURG RENSSELAER COUNTY | Construction - Highway | 03/12/2014 |
New York State Thruway Authority | D214293 |
$804,477.95
|
$0.00 |
04/24/2014 | 12/31/2014 | Rehab of four large culverts Albany Division | Construction - Highway | 04/24/2014 |
New York State Thruway Authority | D214301 |
$1,264,310.22
|
$0.00 |
08/01/2014 | 12/31/2014 | SOIL STABILIZATION ALBANY DIVISION | Construction - Highway | 08/01/2014 |
Department of Environmental Conservation | D009412 |
$1,189,798.31
|
$1,100,371.32 |
09/16/2014 | 11/14/2015 | PUTNAM POND CAMPGROUND ROAD RECONSTRUCTION TICONDEROGA ESSEX COUNTY | Construction - Highway | 09/16/2014 |
New York State Canal Corporation | D214347 |
$1,045,836.42
|
$0.00 |
01/26/2015 | 05/20/2016 | Lock E16 access road and rocky rift dam cutoff wall- Montgomery and Herkimer counties | Construction - Miscellaneous | 01/26/2015 |
Department of Transportation | D263140 |
$2,690,931.10
|
$2,690,931.10 |
05/17/2016 | 06/30/2017 | Intersection Improvement Rt 26 at Oneida/Ontario Ave at Form Drum, Town of LeRay Jefferson County | Construction - Highway | 05/17/2016 |
Department of Transportation | D263206 |
$1,127,844.33
|
$1,127,844.33 |
07/06/2016 | 06/30/2017 | ROCK CATCHMENT FENCE & SLOPE CONTRACT RTS, 171,28,5, HERKIMER & MONTGOMERY COUNTY | Construction - Highway | 07/06/2016 |
Office of Parks Recreation & Historic Preservation | D005299 |
$1,613,732.00
|
$1,611,181.92 |
02/16/2018 | 06/14/2019 | Erie Canalway Trail construct, Amsterdam to Pattersonville, Montgomery/Schenectady Counties | Construction - Highway | 02/16/2018 |
Department of Transportation | D263688 |
$1,357,114.79
|
$1,357,114.79 |
06/06/2018 | 12/31/2018 | Route 9N Hurricane Irene Damage & Drainage Improvements Ausable & Black Brooke, Clinton County | Construction - Highway | 06/06/2018 |
Department of Transportation | D264112 |
$2,835,536.96
|
$2,835,536.96 |
02/24/2020 | 12/31/2021 | Large Culvert Repair & Replace Routes 4,22,9N & I-87 Various Locations Essex, Warren & Washington Co | Construction - Highway | 02/24/2020 |
Department of Transportation | D264368 |
$3,533,666.80
|
$3,533,666.80 |
01/29/2021 | 12/31/2022 | Culvert repairs replacements 2020 2021 Essex & Warren Counties | Construction - Highway | 01/29/2021 |
Department of Transportation | D265092 |
$503,500.00
|
$0.00 |
09/15/2023 | 12/31/2025 | Standby where & when highway maintenance FY 2023 Region 7 in various counties | Construction - Standby Contracts | 09/15/2023 |
Department of Transportation | D265131 |
$979,979.97
|
$56,674.55 |
12/21/2023 | 11/30/2024 | Culvert repairs & replacement at various locations in Herkimer County | Construction - Highway | 12/21/2023 |