Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DEB628V |
$106,000.00
|
$103,904.00 |
08/29/2011 | 12/27/2011 | INSTALL EMERGENCY GENERATOR FOR HURRICANE IRENE PERRY B DURYEA SOB | Construction - Building | 09/26/2011 |
Office of General Services - Design & Construction | DEB662V |
$200,000.00
|
$108,967.00 |
09/08/2011 | 01/06/2012 | REPAIR ELECTRICAL SYSTEMS DAMAGE HURRICANE IRENE SUNKEN MEADOW STATE PARK | Construction - Miscellaneous | 09/27/2011 |
Office of General Services - Design & Construction | DEB617V |
$300,000.00
|
$250,092.00 |
08/18/2011 | 10/08/2012 | INVESTIGATE & REPAIR BROKEN SWITCHGEAR PERRY B DURYEA SOB | Construction - Building | 03/08/2012 |
Office of General Services - Design & Construction | DEB862V |
$115,000.00
|
$97,350.00 |
03/01/2012 | 06/29/2012 | RESTORE POWER TO ADMINISTRATION BUILDING & CENTRAL MALL CONCESSION JONES BEACH STATE PARK | Construction - Building | 05/22/2012 |
Office of General Services - Design & Construction | DEB964V |
$300,000.00
|
$22,247.00 |
06/22/2012 | 10/20/2012 | REMEDIATE LOSS OF ELECTRICAL EQUIPMENT DUE TO FIRE PERRY B DURYEA STATE OFFICE BUILDING | Construction - Building | 07/25/2012 |
Office of General Services - Design & Construction | DEC089V |
$300,000.00
|
$24,728.00 |
10/31/2012 | 02/28/2013 | INSTALL SUNY PROVIDED EMERGENCY GENERATORS AND RESTORE FLOOD DAMAGED GENERATOR OLD WESTBURY CAMPUS | Construction - Building | 12/14/2012 |
Office of General Services - Design & Construction | DEC249V |
$300,000.00
|
$93,510.00 |
02/20/2013 | 12/12/2013 | REPLACE HURRICANE DAMAGED TRANSFORMERS AND SWITCHES HECKSCHER STATE PARK | Construction - Building | 03/12/2013 |
Office of General Services - Design & Construction | DEC699E |
$300,000.00
|
$1,865.00 |
07/25/2014 | 11/22/2014 | RESTORE FAILED ELECTRICAL BREAKER PILGRIM PSYCHIATRIC CENTER SUFFOLK COUNTY | Construction - Building | 08/19/2014 |
Office of General Services - Design & Construction | DEC729V |
$90,000.00
|
$11,233.00 |
08/28/2014 | 12/26/2014 | INVESTIGATE REPLACE FAILED BATTERIES POWERHOUSE PILGRIM PC WEST BRENTWOOD SUFFOLK COUNTY | Construction - Building | 09/25/2014 |
Office of General Services - Design & Construction | DED212V |
$193,908.00
|
$191,705.00 |
05/20/2016 | 10/05/2016 | Investigate/restore Electrical service, Jones Beach SP | Construction - Building | 06/29/2016 |
Office of General Services - Design & Construction | DED223V |
$300,000.00
|
$32,000.00 |
05/29/2016 | 09/26/2016 | Repair high voltage feed to E. Comfort station, Wildwood SP | Construction - Miscellaneous | 06/30/2016 |
Office of General Services - Design & Construction | DED275V |
$300,000.00
|
$51,832.00 |
08/12/2016 | 12/30/2016 | REPAIR HIGH VOLTAGE FEEDER, BRONX PC | Construction - Building | 09/13/2016 |
Office of General Services - Design & Construction | DED846V |
$300,000.00
|
$87,899.00 |
06/14/2018 | 10/12/2018 | Restore Power Multiple Locations Nissequogue River State Park Suffolk County | Construction - Building | 09/07/2018 |
Office of General Services - Design & Construction | DEE396V |
$150,000.00
|
$16,308.00 |
07/24/2020 | 11/21/2020 | Correct electrical issues Bronx PC 1500 Water Pl Bronx Bronx County | Construction - Building | 09/25/2020 |