Department of Environmental Conservation | D009852 |
$1,076,000.00
|
$1,071,237.00 |
08/31/2015 | 08/09/2016 | LEWEY LAKE CG SHOWER BUILDINGS, LAKE PLEASANT, HAMILTON CO (GC) | Construction - Building | 08/31/2015 |
Office of General Services - Design & Construction | DEE663C |
$75,000.00
|
$2,906.95 |
10/06/2021 | 02/03/2022 | Repair damaged ceiling library Wadsworth Center Empire State Plaza Albany County | Construction - Building | 11/17/2021 |
Office of General Services - Design & Construction | D44186C |
$521,993.00
|
$505,661.00 |
09/20/2013 | 12/17/2015 | Provide ventilation, Main School Bldgs Green & Washington CF @ Various DCS Facilities | Construction - Building | 09/20/2013 |
Office of General Services - Design & Construction | D46040C |
$762,300.00
|
$108,735.00 |
05/27/2022 | 03/16/2024 | Provide Sub-headquarters & Loader Storage Building #4 DOT Region 8 Valatie Columbia County | Construction - Building | 05/27/2022 |
Office of General Services - Design & Construction | D45234C |
$829,579.00
|
$828,004.00 |
05/23/2019 | 05/25/2021 | Provide Facility Wide CCTV Audio Monitoring&Recording Rm Bldg Addn Great Meadow CF Washington County | Construction - Building | 05/23/2019 |
Office of General Services - Design & Construction | D43585C |
$32,297.00
|
$31,588.00 |
05/03/2012 | 01/23/2014 | Replace Switchgear, Building 22, State Office Building Campus, Albany | Construction - Building | 05/03/2012 |
Office of General Services - Design & Construction | D45145C |
$216,667.00
|
$210,490.00 |
03/20/2015 | 12/15/2015 | Provide Dry Food Storage Building, Walk-In Cooler & Freezer, Red Hook Residential Center | Construction - Building | 03/20/2015 |
Office of General Services - Design & Construction | DED205C |
$50,000.00
|
$16,152.00 |
05/04/2016 | 09/01/2016 | Repair/Replace Foundation Wall Building 81 Hudson CF Columbia County Emergency Construction | Construction - Building | 05/16/2016 |
Office of General Services - Design & Construction | D44370C |
$416,600.00
|
$415,096.00 |
10/15/2012 | 08/09/2014 | PROVIDE UTILITIES AND FOUNDATION VISIT PROCESS BUILDING AT GREENE CORRECTIONAL FACILITY | Construction - Building | 10/15/2012 |
Office of General Services - Design & Construction | D45465C |
$662,099.00
|
$628,355.00 |
07/02/2018 | 03/30/2020 | Upgrade Elevators Sheridan Avenue Steam Plant C Albany County | Construction - Building | 07/02/2018 |
Office of General Services - Design & Construction | D45259C |
$2,657,900.00
|
$2,656,484.00 |
05/08/2019 | 01/20/2021 | Replace Windows Boilers & HVAC Renovations Units 1 Through 4 & Medical Wing Brookwood SC Columbia Co | Construction - Building | 05/08/2019 |
Office of General Services - Design & Construction | D45620C |
$124,300.00
|
$115,870.00 |
01/07/2019 | 01/16/2020 | Replace Audio Components Convention Center ESP Albany County | Construction - Building | 01/07/2019 |
Office of General Services - Design & Construction | DQ1610C |
$228,258.00
|
$228,024.00 |
03/19/2015 | 01/13/2016 | Replace Emergency Exit Military Museum State Armory Saratoga County | Construction - Building | 03/19/2015 |
Office of General Services - Design & Construction | DQ1511C |
$116,968.00
|
$116,963.00 |
10/05/2011 | 06/01/2012 | REPLACE MESS HALL FLOOR ALBANY TRAINING ACADEMY CORRECTIONAL FACILITY | Construction - Building | 10/05/2011 |
Office of General Services - Design & Construction | D47139C |
$1,469,521.00
|
$1,468,996.00 |
09/24/2021 | 09/27/2022 | Construct SOEK storage facility Washington Correctional Annex Bldg Comstock Washington County | Construction - Building | 09/24/2021 |
Office of General Services - Design & Construction | D44893C |
$724,900.00
|
$721,072.00 |
12/04/2015 | 12/27/2016 | REHABILITATE PEDESTRIAN BRIDGES, BLDG 24, STATE OFFICE BLDG CAMPUS, ALBANY NY | Construction - Building | 12/04/2015 |
Office of General Services - Design & Construction | D45514C |
$176,950.00
|
$175,703.00 |
03/15/2019 | 11/08/2019 | Provide Dry Food Storage Bldg Columbia SC Columbia County | Construction - Building | 03/15/2019 |
Office of General Services - Design & Construction | DEE869C |
$400,000.00
|
$280,324.50 |
08/31/2022 | 06/07/2023 | Repair doors SOB Campus Bldg 4 Albany County Region 4 | Construction - Building | 10/06/2022 |
Office of General Services - Design & Construction | D46087C |
$2,064,000.00
|
$1,591,116.51 |
02/07/2023 | 01/12/2026 | Control room expansion & security upgrades Brookwood Secure Center Columbia County | Construction - Building | 02/07/2023 |
Office of General Services - Design & Construction | D45957C |
$2,477,332.00
|
$630,179.46 |
06/16/2023 | 10/04/2024 | Renovate 41st Floor Corning Tower Empire State Plaza Albany County | Construction - Building | 06/16/2023 |
Office of General Services - Design & Construction | D43728C |
$434,594.00
|
$434,257.00 |
10/27/2009 | 08/27/2012 | PROVIDE JUDGES CHAMBERS, PLATFORM LEVEL THE ROBERT ABRAMS BUILDING FOR LAW AND JUSTICE | Construction - Building | 10/27/2009 |
Office of General Services - Design & Construction | D45098C |
$161,400.00
|
$160,434.00 |
10/31/2016 | 04/02/2019 | New contract, Rehab elevators, State ED Bldg, Albany | Construction - Building | 10/31/2016 |
Office of General Services - Design & Construction | D43334C |
$519,064.00
|
$519,064.00 |
08/02/2010 | 06/27/2012 | REPAIR / REPLACE DOORS FRAMES & HARDWARE HUDSON CF | Construction - Building | 12/30/2011 |
Office of General Services - Design & Construction | D45290C |
$347,200.00
|
$347,200.00 |
03/10/2016 | 01/04/2017 | Miscellaneous Upgrades, Fleet Administration Shop, DOT Region 1, Saratoga County | Construction - Building | 03/10/2016 |
Office of General Services - Design & Construction | DEC009G |
$150,000.00
|
$15,576.00 |
08/20/2012 | 12/18/2012 | INVESTIGATE/REPAIR SINK HOLE GREAT MEADOW CF | Construction - Building | 09/19/2012 |
Office of General Services - Design & Construction | D46133C |
$7,187,855.00
|
$6,746,473.00 |
08/24/2020 | 10/15/2023 | New classrooms & office spaces Bldg 45 Greene Correctional Facility Greene County | Construction - Building | 08/24/2020 |
Office of General Services - Design & Construction | D45356C |
$248,000.00
|
$235,857.00 |
05/11/2020 | 02/09/2021 | Provide Expresstop Building 4 State Office Building Campus Albany County | Construction - Building | 05/11/2020 |
Office of General Services - Design & Construction | DQ1576C |
$1,350,033.00
|
$1,311,741.00 |
03/20/2015 | 09/30/2016 | REMEDIATE LEAD & REPLACE FINISHES & UPGRADE ELECTRICAL, NYS ARMORY, TROY NY | Construction - Building | 03/20/2015 |
Office of General Services - Design & Construction | D47214C |
$338,736.00
|
$331,300.00 |
08/25/2022 | 07/09/2024 | Provide system upgrades Saratoga Military Museum State Armory Saratoga County | Construction - Building | 08/25/2022 |
Office of Parks Recreation & Historic Preservation | D004339 |
$864,600.00
|
$864,600.00 |
08/21/2013 | 06/27/2014 | Comfort Stations Phase II, Lot-A and Lot-F @ Lake Taghkanic State Park General Construction | Construction - Building | 08/21/2013 |
State University Construction Fund | T006386 |
$4,504,835.00
|
$4,504,835.00 |
01/11/2018 | 01/11/2020 | SUCF241010 Renovate Bouck The | Contracts Not Subject to OSC Pre-Audit | 01/17/2018 |