State University Construction Fund | D006780 |
$1,798,729.00
|
$1,247,478.00 |
11/23/2022 | 05/06/2025 | Upgrade electrical substation for McMahon Hall at the College of Ceramics at Alfred University | Construction - Building | 11/18/2022 |
Office of General Services - Design & Construction | D41999E |
$1,582,826.00
|
$1,579,104.00 |
06/30/2004 | 12/31/2011 | ARTHURKILL CF, REPLACE FACILITY SWITCHGEAR | Construction - Building | 11/16/2011 |
Office of General Services - Design & Construction | D42715E |
$88,533.00
|
$87,399.00 |
08/01/2007 | 01/27/2009 | PROVIDE YARD LIGHTING SING SING CORRECTIONAL FACILITY | Construction - Building | 10/30/2008 |
Office of General Services - Design & Construction | D44069E |
$770,867.00
|
$769,578.00 |
05/18/2011 | 05/23/2013 | REPLACE TRANSFORMERS, BASEMENT, BLDG 15 ATTICA CF | Construction - Building | 03/20/2012 |
Office of General Services - Design & Construction | D44750E |
$2,827,951.00
|
$2,827,731.00 |
11/15/2017 | 12/10/2021 | Replace Switchgear, Altona Correctional Facility, Clinton County | Construction - Building | 11/15/2017 |
Office of General Services - Design & Construction | D45210E |
$3,484,285.00
|
$3,474,145.00 |
03/15/2019 | 11/07/2021 | Replace Generator & Switchgear Building 20 & 43 Franklin CF Franklin County E | Construction - Building | 03/15/2019 |
Office of General Services - Design & Construction | D45390E |
$7,816,229.00
|
$0.00 |
03/22/2024 | 06/20/2026 | Upgrade generator & switchgear at Mohawk Correctional Facility in Oneida County | Construction - Building | 03/22/2024 |
Office of General Services - Design & Construction | DEB226V |
$200,000.00
|
$63,623.00 |
06/11/2010 | 04/29/2011 | REPLACE FAILED TRANSFORMER ADMIN BLDG #71 FINGER LAKES DDSO | Construction - Building | 10/07/2010 |
Office of General Services - Design & Construction | DEB272V |
$300,000.00
|
$26,353.00 |
07/21/2010 | 06/29/2011 | REPAIR FAILED ELECTRICAL LINE WYOMING CF | Construction - Building | 11/17/2010 |
Office of General Services - Design & Construction | DEB297V |
$300,000.00
|
$142,342.00 |
08/12/2010 | 07/27/2011 | REPAIR FAILING EMERGENCY GENERATOR WENDE CF | Construction - Building | 12/09/2010 |
Office of General Services - Design & Construction | DEB323V |
$75,000.00
|
$6,205.00 |
09/20/2010 | 05/18/2011 | REPAIR FAILED EMERGENCY GENERATOR ANNEX BLDG LAKEVIEW CF | Construction - Building | 10/14/2010 |
Office of General Services - Design & Construction | DEB384V |
$200,000.00
|
$26,632.00 |
10/29/2010 | 08/25/2011 | INVESTIGATE/REPAIR SWITCHGEAR MALFUNCTION CHATEAUGAY CF | Construction - Building | 03/04/2011 |
Office of General Services - Design & Construction | DEB406V |
$75,000.00
|
$33,847.00 |
11/24/2010 | 10/12/2011 | REPAIR FAILING EMERGENCY GENERATOR RIVERVIEW CF | Construction - Building | 04/06/2011 |
Office of General Services - Design & Construction | DEB409V |
$300,000.00
|
$49,564.00 |
12/01/2010 | 08/04/2011 | INVESTIGATE/RESTORE FAILED POWER WATERTOWN CF | Construction - Building | 08/22/2011 |
Office of General Services - Design & Construction | DEB455V |
$260,000.00
|
$217,705.00 |
01/13/2011 | 07/20/2011 | REPAIR EMERGENCY GENERATOR PUMP INSTITUTE FOR BASIC RESEARCH | Construction - Building | 09/22/2011 |
Office of General Services - Design & Construction | DEB512V |
$300,000.00
|
$94,673.00 |
03/18/2011 | 09/30/2011 | RESTORE FAILED EMERGENCY GENERATOR BLDG 105 CREEDMOOR PC | Construction - Building | 10/26/2011 |
Office of General Services - Design & Construction | DEB527V |
$300,000.00
|
$161,364.00 |
04/18/2011 | 08/16/2011 | RESTORE POWER TO CELL BLOCK A SING SING CF | Construction - Building | 05/16/2011 |
Office of General Services - Design & Construction | DEB536V |
$300,000.00
|
$293,463.00 |
05/03/2011 | 08/31/2011 | REPAIR ELECTRICAL FEEDER TO RESTORE POWER PURCHASE SUC | Construction - Building | 06/01/2011 |
Office of General Services - Design & Construction | DEB565V |
$300,000.00
|
$190,970.00 |
06/15/2011 | 05/09/2012 | REPLACE EMERGENCY GENERATOR BINGHAMTON SOB | Construction - Building | 01/20/2012 |
Office of General Services - Design & Construction | DEB569V |
$150,000.00
|
$67,385.00 |
06/18/2011 | 10/16/2011 | REPAIR SWITCH GEAR TO RESTORE POWER ALTONA CF | Construction - Building | 07/26/2011 |
Office of General Services - Design & Construction | DEB621V |
$220,000.00
|
$217,272.00 |
08/19/2011 | 06/27/2012 | RESTORE FAILED BACKUP GENERATOR BLDG 56 QUEENS CPC | Construction - Building | 01/09/2012 |
Office of General Services - Design & Construction | DEB756V |
$75,000.00
|
$43,625.00 |
11/02/2011 | 03/01/2012 | REPAIR FAILED COOLING FAN ON EMERGENCY GENERATOR RIVERVIEW CF | Construction - Building | 12/05/2011 |
Office of General Services - Design & Construction | DEB793V |
$100,000.00
|
$54,391.00 |
12/27/2011 | 02/15/2013 | REPAIR/REPLACE DAMAGED 100KVA TRANSFORMER AUBURN CF | Construction - Building | 01/23/2012 |
Office of General Services - Design & Construction | DEB822V |
$300,000.00
|
$34,939.00 |
01/18/2012 | 05/17/2012 | RESTORE FAILED FEEDER #59 SWITCHGEAR HUTCHINGS PC | Construction - Building | 02/13/2012 |
Office of General Services - Design & Construction | DEB837V |
$190,923.00
|
$190,844.00 |
02/07/2012 | 09/19/2013 | REPAIR VOLTAGE IRREGULARITIES TO BACK UP GENERATOR RIVERVIEW CF | Construction - Building | 02/28/2012 |
Office of General Services - Design & Construction | DEC042V |
$300,000.00
|
$299,566.00 |
10/01/2012 | 03/30/2013 | REHAB ELECTRICAL DISTRIBUTION SYSTEM GILBERT LAKE STATE PARK | Construction - Building | 11/05/2012 |
Office of General Services - Design & Construction | DEC075V |
$175,000.00
|
$10,105.00 |
10/30/2012 | 02/27/2013 | REPAIR /REPLACE POWER POLES & RESTORE POWER DUE TO HURRICANE SANDY DAMAGE TACONIC CF | Construction - Building | 12/04/2012 |
Office of General Services - Design & Construction | DEC091V |
$450,000.00
|
$103,750.00 |
10/31/2012 | 11/30/2014 | RESTORE ELECTRICAL SYSTEMS VARIOUS BUILDINGS SING SING CF | Construction - Building | 12/04/2012 |
Office of General Services - Design & Construction | DEC112V |
$200,000.00
|
$20,744.00 |
11/02/2012 | 03/02/2013 | PROVIDE BACK-UP GENERATOR ST ALBANS VETERANS HOME HURRICANE SANDY | Construction - Building | 12/10/2012 |
Office of General Services - Design & Construction | DEC199V |
$2,250,000.00
|
$2,236,988.00 |
02/19/2013 | 12/31/2014 | RESTORE FAILED ELECTRICAL SERVICE FEEDER SOUTH BEACH PC | Construction - Building | 03/11/2013 |
Office of General Services - Design & Construction | DEC223V |
$200,000.00
|
$25,991.00 |
02/01/2013 | 07/19/2013 | RESTORE FAILED ATS CONTROLS FOR ELECTRICAL POWER IN BUILDING 82 AT PILGRIM PC | Construction - Building | 03/08/2013 |
Office of General Services - Design & Construction | DEC267V |
$300,000.00
|
$198,258.00 |
03/01/2013 | 09/20/2013 | REHAB ELECTRICAL DISTRIBUTION SYSTEM AT GILBERT LAKE STATE PARK LAURENTS NY | Construction - Building | 06/05/2013 |
Office of General Services - Design & Construction | DEC345V |
$75,000.00
|
$10,766.00 |
05/30/2013 | 09/27/2013 | RESTORE ELECTRICAL POWER CAMP GABRIELS | Construction - Building | 07/12/2013 |
Office of General Services - Design & Construction | DEC399V |
$300,000.00
|
$296,780.00 |
07/22/2013 | 11/19/2013 | REPAIR FIRE DAMAGED HIGH VOLTAGE SWITCH GEAR CAMP SMITH CORLANDT MANOR | Construction - Building | 08/14/2013 |
Office of General Services - Design & Construction | DEC407V |
$300,000.00
|
$279,868.00 |
07/30/2013 | 11/27/2013 | CLEAN & REPAIR FIRE DAMAGED HIGH VOLTAGE SWITCHGEAR CAMP SMITH | Construction - Building | 08/28/2013 |
Office of General Services - Design & Construction | DEC408V |
$300,000.00
|
$249,468.00 |
07/30/2013 | 11/27/2013 | CLEAN & REPAIR HIGH VOLTAGE SWITCHGEAR CAMP SMITH | Construction - Building | 08/30/2013 |
Office of General Services - Design & Construction | DEC475V |
$300,000.00
|
$11,192.00 |
10/25/2013 | 02/22/2014 | INVESTIGATE AND CORRECT GFI FAULT WILLARD DRUG TREATMENT CENTER | Construction - Building | 12/06/2013 |
Office of General Services - Design & Construction | DEC558V |
$300,000.00
|
$37,898.00 |
02/06/2014 | 06/06/2014 | REPAIR FAULTS ON FAILED ELECTRICAL FEEDER 1 BRONX PC | Construction - Building | 03/25/2014 |
Office of General Services - Design & Construction | DEC633V |
$100,000.00
|
$36,298.00 |
05/13/2014 | 11/19/2014 | REPAIR FAILED POWER FEED KIRBY FORSENIC BLDG MANHATTAN PC | Construction - Building | 06/05/2014 |
Office of General Services - Design & Construction | DEC646V |
$300,000.00
|
$32,238.00 |
05/21/2014 | 10/28/2014 | INVESTIGATE & REPAIR PROBLEMATIC TRANSFER SWITCH LAKEVIEW CF CHAUTAUQUA COUNTY | Construction - Building | 06/16/2014 |
Office of General Services - Design & Construction | DEC684V |
$300,000.00
|
$89,249.00 |
07/02/2014 | 10/30/2014 | RESTORE FAULTY FEEDER 1 & PROVIDE TEMPORARY GENERATORS BUILDING 11 12 & 13 BRONX PC BRONX COUNTY | Construction - Building | 08/06/2014 |
Office of General Services - Design & Construction | DEC734V |
$300,000.00
|
$189,113.00 |
09/12/2014 | 12/31/2016 | CORRECT FAILED POWER FEEDERS BUILDING 122 MANHATTAN PC NY COUNTY | Construction - Building | 10/07/2014 |
Office of General Services - Design & Construction | DEC749V |
$300,000.00
|
$282,624.00 |
10/06/2014 | 05/04/2015 | RESTORE EMERGENCY POWER VIA PORTABLE GENERATOR RENTAL BEDFORD HILLS CF WESTCHESTER COUNTY | Construction - Building | 11/03/2014 |
Office of General Services - Design & Construction | DEC796V |
$300,000.00
|
$111,070.00 |
11/24/2014 | 05/15/2015 | REPLACE FAILED TRANSFORMER BLDG 2 & 25 DELHI SUATC DELAWARE COUNTY | Construction - Building | 01/23/2015 |
Office of General Services - Design & Construction | DEC894V |
$300,000.00
|
$291,671.00 |
03/18/2015 | 07/16/2015 | Investiage & Restore Power, Various Buildings, Cobleskill SUATC | Construction - Building | 04/17/2015 |
Office of General Services - Design & Construction | DEC982V |
$150,000.00
|
$3,731.00 |
07/23/2015 | 12/20/2015 | Investigate/Restore Power, Switchgear Room, Building 47, Rockland PC | Construction - Building | 08/27/2015 |
Office of General Services - Design & Construction | DED088V |
$300,000.00
|
$95,919.00 |
12/16/2015 | 05/03/2017 | Investigate & Repair Failed Feeder #2, Electrical | Construction - Building | 01/08/2016 |
Office of General Services - Design & Construction | DED159V |
$300,000.00
|
$33,216.00 |
02/18/2016 | 10/31/2016 | Investigate and Replace Main Utility Breaker, Five Points CF | Construction - Building | 03/18/2016 |
Office of General Services - Design & Construction | DED192V |
$550,000.00
|
$494,529.00 |
04/06/2016 | 10/03/2016 | Repair Failed Backup Generator, Staten Island DDSO | Construction - Building | 04/21/2016 |
Office of General Services - Design & Construction | DED220V |
$300,000.00
|
$153,028.00 |
05/24/2016 | 09/21/2016 | REPAIR 5KV FEEDER AT RED COURSE, BETHPAGE SP | Construction - Building | 06/30/2016 |