Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DEA791H |
$300,000.00
|
$277,622.00 |
05/15/2009 | 11/11/2009 | REPLACE LEAKING DEARATOR TANK & APPURTENANCES GROVELAND CF | Construction - Building | 06/24/2009 |
Office of General Services - Design & Construction | DEA977H |
$300,000.00
|
$284,284.00 |
10/19/2009 | 04/17/2010 | REPLACE FAILED DEAREATOR BLDG 146 GROVELAND CF | Construction - Building | 11/13/2009 |
Office of General Services - Design & Construction | DM2773N |
$78,624.00
|
$77,975.00 |
09/29/2008 | 05/01/2010 | PROVIDE FIRE SUPPRESSION SYSTEM IN KITCHEN HOOD, BLDG. NO. 12 WYOMING CF | Construction - Building | 11/10/2009 |
Office of General Services - Design & Construction | DEA993H |
$300,000.00
|
$179,011.00 |
11/04/2009 | 07/02/2010 | REPAIR HVAC AND PROVIDE TEMP HEAT IN BLDG 56 COLLINS CF | Construction - Building | 12/01/2009 |
State University Construction Fund | T005457 |
$57,146.00
|
$57,146.00 |
03/04/2009 | 08/14/2010 | UPGRADE HVAC SYSTEM - HARDER HALL AT SUNY ALFRED CERAMICS - PROJECT 35108 | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of General Services - Design & Construction | DEB108H |
$75,000.00
|
$7,517.00 |
02/12/2010 | 10/10/2010 | REPLACE LEAKING DEAEREATOR TANK & APPURTANCES GROVELAND CF | Construction - Building | 02/16/2011 |
State University Construction Fund | T005484 |
$59,122.00
|
$59,122.00 |
04/20/2009 | 11/01/2010 | INFRASTRUCTURE IMPROVEMENTS SUCF 06330 MERRITT HALL SUNY GENESEO | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of General Services - Design & Construction | DEB218H |
$100,000.00
|
$25,152.00 |
06/01/2010 | 11/08/2010 | REPAIR FAILED AIR CONDITIONING BLDG 1 LAKEVIEW CF | Construction - Building | 07/02/2010 |
Office of General Services - Design & Construction | DEB267H |
$100,000.00
|
$13,981.00 |
07/16/2010 | 11/13/2010 | REPAIR FAILED AIR CONDITIONING SYSTEM BLDG 2 LAKEVIEW CF | Construction - Building | 08/26/2010 |
Office of General Services - Design & Construction | DEB228P |
$100,000.00
|
$9,823.00 |
06/15/2010 | 11/30/2010 | REPAIR/REPLACE FAILED DOMESTIC HOT WATER HEATER GOWANDA CF | Construction - Building | 05/05/2011 |
State University Construction Fund | T005393 |
$12,058.00
|
$12,058.00 |
05/14/2008 | 12/01/2010 | SUCF 35115 ALFRED CERAMICS ABATE ASBESTOS/MODIFY HVAC - HARDER HALL | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of General Services - Design & Construction | D42359H |
$1,227,837.00
|
$1,182,951.00 |
05/20/2008 | 12/02/2010 | UPGRADE PLUMBING & HEATING ALBION CF | Construction - Building | 07/20/2010 |
College at Fredonia | T000171 |
$173,169.00
|
$173,169.00 |
08/13/2010 | 04/15/2011 | PROJECT I00718 (05315) LOGRASSO HALL EMERGENCY GENERATOR REPLACEMENT | Contracts Not Subject to OSC Pre-Audit | 11/23/2010 |
Office of General Services - Design & Construction | D43783H |
$333,000.00
|
$322,331.00 |
08/24/2009 | 06/21/2011 | REPLACE DOMESTIC HOT WATER TANKS WENDE CF | Construction - Building | 08/24/2009 |
Office of General Services - Design & Construction | DEB484H |
$300,000.00
|
$32,668.00 |
02/10/2011 | 07/27/2011 | REPLACE FAILED HEAT EXCHANGER SUNY ALFRED | Construction - Building | 11/28/2011 |
Office of General Services - Design & Construction | DEB258H |
$250,000.00
|
$175,274.00 |
07/07/2010 | 11/15/2011 | REPAIR/REPLACE FAILED AC UNIT ADMIN BLDG WYOMING CF | Construction - Building | 12/29/2011 |
Office of General Services - Design & Construction | DQ1274H |
$390,150.00
|
$361,331.00 |
03/31/2010 | 02/28/2012 | PROVIDE AIR INTAKES, HOUSING BLOCKS, VARIOUS BLDGS FIVE POINTS CF | Construction - Building | 07/07/2011 |
SUNY at Buffalo | T000423 |
$454,102.00
|
$454,102.00 |
02/11/2011 | 03/15/2012 | PROJECT 2010-135 TITLED GOVERNOR'S DORMS - REPLACE ROTOCLONE | Contracts Not Subject to OSC Pre-Audit | 02/08/2012 |
SUNY at Buffalo | T000275 |
$250,000.00
|
$198,450.56 |
07/01/2009 | 06/30/2012 | HVAC-STEAM-MECHANICAL SERVICES | Contracts Not Subject to OSC Pre-Audit | 08/11/2009 |
Office of General Services - Design & Construction | D42795H |
$169,494.00
|
$167,713.00 |
10/19/2007 | 07/13/2012 | REPLACE SHOWER BLDGS. 9-11, 13-16 WENDE CF | Construction - Building | 12/07/2011 |
Office of General Services - Design & Construction | DQ1391P |
$59,000.00
|
$53,600.00 |
11/08/2010 | 08/12/2012 | REHAB SHOP AREA FMS #1 BUFFALO ARMORY, MASTEN | Construction - Building | 11/08/2010 |
College of Ceramics at Alfred University | T035122 |
$102,000.00
|
$100,980.00 |
07/16/2012 | 08/24/2012 | NEON SHOP VENTILATION AND SAFE | Contracts Not Subject to OSC Pre-Audit | 07/13/2012 |
Office of General Services - Design & Construction | D44127H |
$158,300.00
|
$150,781.00 |
08/04/2011 | 09/18/2012 | PROVIDE VENTILATION SYSTEM - ROOM 1-27, BLDG 4 LIVINGSTON CF | Construction - Building | 08/04/2011 |
Office of General Services - Design & Construction | DQ1381H |
$369,950.00
|
$366,400.00 |
09/24/2009 | 10/01/2012 | REPLACE BOILERS LOCKPORT ARMORY | Construction - Building | 03/06/2012 |
College of Ceramics at Alfred University | T881300 |
$1,571,747.00
|
$891,173.20 |
05/14/2012 | 12/31/2012 | KILN ROOM HVAC RENOVATION | Contracts Not Subject to OSC Pre-Audit | 05/17/2012 |
Office of General Services - Design & Construction | DEA980P |
$300,000.00
|
$197,515.00 |
10/20/2009 | 01/11/2013 | INSTALL CODE REQUIRED TURBIDITY MONITORS & EQUIP GROVELAND CF | Construction - Building | 02/14/2012 |
SUNY at Buffalo | T000213 |
$250,000.00
|
$12,374.94 |
05/01/2008 | 04/30/2013 | MOLD/LEAD REMEDIATION - HVAC CLEANING | Contracts Not Subject to OSC Pre-Audit | 08/13/2008 |
Office of General Services - Design & Construction | D41820H |
$29,350.00
|
$28,450.00 |
09/24/2008 | 06/17/2013 | UPGRADE ELECTRICAL SITE DISTRIBUTION SYSTEM AND GENERATORS @ GROVELAND CF | Construction - Building | 09/24/2008 |
Office of General Services - Design & Construction | D43946H |
$39,800.00
|
$39,102.00 |
10/29/2010 | 10/14/2013 | PROVIDE HANDICAP ACCESSIBILITY,PHASE 2, VAR.BLDGS WENDE CF | Construction - Building | 10/29/2010 |
Office of General Services - Design & Construction | DEC495H |
$300,000.00
|
$150,332.00 |
11/19/2013 | 09/10/2014 | REPAIR WATER MAIN LEAK BUILDING 7 WYOMING CF | Construction - Building | 12/27/2013 |
Office of General Services - Design & Construction | D44470H |
$34,000.00
|
$32,000.00 |
06/05/2013 | 11/16/2014 | REPLACE ROOF HVAC WORK ADMINISTRATION BUILDING WYOMING CF | Construction - Building | 06/05/2013 |
Office of General Services - Design & Construction | D44182H |
$308,000.00
|
$292,426.00 |
04/24/2013 | 12/12/2014 | PROVIDE VENTILATION SYSTEM VOCATIONAL SMALL ENGINE SHOP BUILDING 153 GROVELAND CORRECTIONAL FACILITY | Construction - Building | 04/24/2013 |
Office of Parks Recreation & Historic Preservation | D004407 |
$2,175,712.96
|
$2,175,712.96 |
12/23/2013 | 09/30/2015 | Admin Bldg/Visitor Center Renovations, Niagara Reservation SP mechanical trade | Construction - Building | 12/23/2013 |
Office of General Services - Design & Construction | D44187H |
$1,199,566.00
|
$1,177,310.00 |
05/20/2013 | 10/05/2015 | PROVIDE VENTILATION, MAIN SCHOOL BUILDING VARIOUS DOCS FACILITIES | Construction - Building | 05/20/2013 |
Office of General Services - Design & Construction | D44674P |
$84,822.00
|
$84,354.00 |
06/05/2014 | 11/27/2015 | REHABI KITCHEN BUILDING 12 PLUMBING WORK CONTRACT LAKEVIEW CF | Construction - Building | 06/05/2014 |
Office of General Services - Design & Construction | DEC947H |
$375,000.00
|
$304,235.00 |
06/03/2015 | 01/29/2016 | REPAIR UNDERGROUND STEAM LINE,SPORTS ARENA HVAC, BUFFALO SUC | Construction - Building | 07/07/2015 |
Office of General Services - Design & Construction | DED008H |
$300,000.00
|
$100,691.00 |
08/24/2015 | 02/20/2016 | INVESTIGATE/RPR DOMESTIC HOT WATER LEAK, MED BLDG, HVAC, LAKEVIEW CF | Construction - Building | 11/09/2015 |
Office of General Services - Design & Construction | D42530H |
$1,850,339.00
|
$1,825,345.00 |
05/15/2013 | 02/21/2016 | HVAC CONSTRUCTION CONTRACT TO UPGRADE HEATING SYSTEMS & WINDOWS BUILDING 2 ATTICA CF | Construction - Building | 05/15/2013 |
Office of General Services - Design & Construction | D44550H |
$1,225,697.00
|
$1,225,596.00 |
01/09/2014 | 02/29/2016 | Update Boiler Controls Bldg 146, Power House @ Groveland CF - Livingston Co. | Construction - Building | 01/09/2014 |
SUNY at Buffalo | C001190 |
$1,893,578.00
|
$1,609,131.22 |
03/31/2011 | 03/30/2016 | HVAC-STEAM-MECHANICAL SERVICES | Service - Building Services | 03/31/2011 |
Office of General Services - Design & Construction | D44745H |
$224,780.00
|
$224,568.00 |
06/11/2014 | 05/26/2016 | Provide Infrared Heating System, Bldgs 2, 3, 4 & 5 @ NYSDOT Facility, Region 5, Mayville | Construction - Building | 06/11/2014 |
Office of General Services - Design & Construction | D44674H |
$291,067.00
|
$290,475.00 |
06/05/2014 | 06/07/2016 | REHAB KITCHEN BUILDING 12 HVAC WORK LAKEVIEW CF | Construction - Building | 06/05/2014 |
Office of General Services - Design & Construction | DEC973H |
$228,800.00
|
$203,800.00 |
08/19/2015 | 06/14/2016 | Repair Leaking 2" Underground Heating Line, Admin Bldg, Wyoming CF, Wyoming County | Construction - Building | 09/17/2015 |
Office of General Services - Design & Construction | D44162H |
$766,344.00
|
$766,334.00 |
03/13/2014 | 06/28/2016 | REPAIR HVAC CONTROLS & SYSTEMS FINGER LAKES RESIDENTIAL CENTER TOMPKINS COUNTY | Construction - Building | 03/13/2014 |
Office of General Services - Design & Construction | D43704H |
$947,450.00
|
$947,441.00 |
09/21/2012 | 07/15/2016 | Rehab Food Service Operations Bldg Nos 3 & 20 @ Wende CF | Construction - Building | 09/21/2012 |
Office of General Services - Design & Construction | D44829H |
$1,032,000.00
|
$1,012,024.50 |
09/23/2014 | 08/10/2016 | REPLACE BOILERS HVAC WORK MAHONEY STATE OFFICE BUILDING BUFFALO | Construction - Building | 09/23/2014 |
Office of General Services - Design & Construction | D44116H |
$627,000.00
|
$624,186.00 |
06/18/2012 | 09/02/2016 | PROVIDE SECURITY WINDOWS AND HEATING SYSTEM CELL BLOCK 'G', BLDG NO 16, WENDE CF | Construction - Building | 06/18/2012 |
Office of General Services - Design & Construction | DED003H |
$472,400.00
|
$422,400.00 |
09/01/2015 | 10/05/2016 | Replace Underground Heating Line, West Compound, Wyoming CF, Wyoming County | Construction - Building | 11/12/2015 |
SUNY at Buffalo | T500061 |
$284,233.00
|
$284,233.00 |
10/13/2015 | 11/01/2016 | PROJECT 2015-138 BAKER CHILLED | Contracts Not Subject to OSC Pre-Audit | 12/01/2015 |
State University Construction Fund | T006150 |
$0.01
|
$0.00 |
05/20/2015 | 12/06/2016 | SUCF 22245 Install Satellite | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |