Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
State University Construction Fund | T006150 |
$0.01
|
$0.00 |
05/20/2015 | 12/06/2016 | SUCF 22245 Install Satellite | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |
Office of General Services - Design & Construction | D44027P |
$9,410.00
|
$9,410.00 |
03/12/2015 | 06/21/2017 | SANITARY SEWER PUMP STATION REPLACEMENT & INFILTRATION / INFLOW REDUCTION, COXSACKIE CF | Construction - Building | 03/12/2015 |
State University Construction Fund | T005393 |
$12,058.00
|
$12,058.00 |
05/14/2008 | 12/01/2010 | SUCF 35115 ALFRED CERAMICS ABATE ASBESTOS/MODIFY HVAC - HARDER HALL | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
SUNY at Buffalo | T000826 |
$12,070.00
|
$5,440.00 |
08/01/2019 | 07/31/2020 | BIOLOGICAL SAFETY CABINET CERT | Contracts Not Subject to OSC Pre-Audit | 09/05/2019 |
Office of General Services - Design & Construction | D45448H |
$15,500.00
|
$14,500.00 |
08/09/2019 | 01/26/2021 | Provide Domestic Water Pump Station State Office Bldg Campus Albany County | Construction - Building | 08/09/2019 |
Office of General Services - Design & Construction | D41820H |
$29,350.00
|
$28,450.00 |
09/24/2008 | 06/17/2013 | UPGRADE ELECTRICAL SITE DISTRIBUTION SYSTEM AND GENERATORS @ GROVELAND CF | Construction - Building | 09/24/2008 |
SUNY at Buffalo | T000782 |
$32,112.50
|
$7,340.00 |
01/01/2019 | 12/31/2019 | TESTING, ADJUSTING AND BALANCI | Contracts Not Subject to OSC Pre-Audit | 02/14/2019 |
Office of General Services - Design & Construction | D44470H |
$34,000.00
|
$32,000.00 |
06/05/2013 | 11/16/2014 | REPLACE ROOF HVAC WORK ADMINISTRATION BUILDING WYOMING CF | Construction - Building | 06/05/2013 |
Office of General Services - Design & Construction | DM3138H |
$38,400.00
|
$36,000.00 |
11/19/2021 | 11/22/2022 | Repair elevator Building 14 Clinton CF Clinton County | Construction - Building | 11/19/2021 |
Office of General Services - Design & Construction | D43946H |
$39,800.00
|
$39,102.00 |
10/29/2010 | 10/14/2013 | PROVIDE HANDICAP ACCESSIBILITY,PHASE 2, VAR.BLDGS WENDE CF | Construction - Building | 10/29/2010 |
Office of General Services - Design & Construction | DQ1661E |
$49,000.00
|
$47,322.00 |
04/27/2016 | 09/06/2017 | Replace Domestic Hot Water Tank & EPDM Roofing, Electric, Building 9, Attica CF | Construction - Building | 04/27/2016 |
State University Construction Fund | T005457 |
$57,146.00
|
$57,146.00 |
03/04/2009 | 08/14/2010 | UPGRADE HVAC SYSTEM - HARDER HALL AT SUNY ALFRED CERAMICS - PROJECT 35108 | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of General Services - Design & Construction | DQ1391P |
$59,000.00
|
$53,600.00 |
11/08/2010 | 08/12/2012 | REHAB SHOP AREA FMS #1 BUFFALO ARMORY, MASTEN | Construction - Building | 11/08/2010 |
State University Construction Fund | T005484 |
$59,122.00
|
$59,122.00 |
04/20/2009 | 11/01/2010 | INFRASTRUCTURE IMPROVEMENTS SUCF 06330 MERRITT HALL SUNY GENESEO | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
Office of General Services - Design & Construction | D45448P |
$60,000.00
|
$58,364.00 |
08/09/2019 | 01/26/2021 | Provide Domestic Water Pump Station State Office Bldg Campus Albany County | Construction - Building | 08/09/2019 |
Livingston Correctional Facility | OP800150189 |
$63,880.00
|
$63,880.00 |
04/01/2016 | 03/31/2017 | Replace Administration Chiller | Service - Building Services | 11/07/2016 |
SUNY at Buffalo | T500129 |
$65,222.00
|
$65,222.00 |
09/26/2019 | 06/20/2020 | CROFTS SECOND FLOOR SOUTH HVAC | Contracts Not Subject to OSC Pre-Audit | 11/07/2019 |
SUNY - Upstate Medical University | T550320 |
$65,700.00
|
$65,700.00 |
11/24/2021 | 03/31/2022 | PROJECT 1362 IHP & NRB STEAM | Contracts Not Subject to OSC Pre-Audit | 12/13/2021 |
Office of General Services - Design & Construction | DM3111P |
$72,300.00
|
$68,520.00 |
11/25/2020 | 01/07/2022 | Replace heating system piping Elmira CF Chemung County | Construction - Miscellaneous | 11/25/2020 |
Office of General Services - Design & Construction | DEE463P |
$75,000.00
|
$3,161.41 |
10/30/2020 | 02/27/2021 | Repair clogged sanitary line Albion Correctional Facility Orleans County | Construction - Building | 12/10/2020 |
Office of General Services - Design & Construction | DEB108H |
$75,000.00
|
$7,517.00 |
02/12/2010 | 10/10/2010 | REPLACE LEAKING DEAEREATOR TANK & APPURTANCES GROVELAND CF | Construction - Building | 02/16/2011 |
Office of General Services - Design & Construction | DEE346H |
$75,000.00
|
$35,696.00 |
05/08/2020 | 09/05/2020 | Repair underground hot water line Hutchings PC bldg 12 620 Madison St Syracuse Onondaga County | Construction - Building | 09/03/2020 |
Office of General Services - Design & Construction | D44945H |
$75,831.00
|
$75,267.00 |
08/21/2015 | 04/19/2017 | upgrade RMU elevators and electrical system, Wende CF. | Construction - Building | 08/21/2015 |
Office of General Services - Design & Construction | DM2773N |
$78,624.00
|
$77,975.00 |
09/29/2008 | 05/01/2010 | PROVIDE FIRE SUPPRESSION SYSTEM IN KITCHEN HOOD, BLDG. NO. 12 WYOMING CF | Construction - Building | 11/10/2009 |
Office of General Services - Design & Construction | D45327H |
$82,000.00
|
$81,699.00 |
01/24/2018 | 07/09/2019 | Provide ADA Upgrades, Building 23, Albion CF Orleans County (H) | Construction - Building | 01/24/2018 |
Office of General Services - Design & Construction | D44674P |
$84,822.00
|
$84,354.00 |
06/05/2014 | 11/27/2015 | REHABI KITCHEN BUILDING 12 PLUMBING WORK CONTRACT LAKEVIEW CF | Construction - Building | 06/05/2014 |
Office of General Services - Design & Construction | DEB267H |
$100,000.00
|
$13,981.00 |
07/16/2010 | 11/13/2010 | REPAIR FAILED AIR CONDITIONING SYSTEM BLDG 2 LAKEVIEW CF | Construction - Building | 08/26/2010 |
Office of General Services - Design & Construction | DEB228P |
$100,000.00
|
$9,823.00 |
06/15/2010 | 11/30/2010 | REPAIR/REPLACE FAILED DOMESTIC HOT WATER HEATER GOWANDA CF | Construction - Building | 05/05/2011 |
Office of General Services - Design & Construction | DEB218H |
$100,000.00
|
$25,152.00 |
06/01/2010 | 11/08/2010 | REPAIR FAILED AIR CONDITIONING BLDG 1 LAKEVIEW CF | Construction - Building | 07/02/2010 |
Office of General Services - Design & Construction | DEE797P |
$100,000.00
|
$2,139.37 |
03/23/2022 | 09/19/2022 | Restore blocked sanitary sewer building 11 Wede CF Erie County Region 7 | Construction - Building | 05/03/2022 |
Office of General Services - Design & Construction | DEF091H |
$100,000.00
|
$17,338.32 |
11/01/2023 | 06/30/2024 | Repair steam leak in Bldg 8 at Clinton Correctional Facility in Clinton County | Construction - Building | 12/18/2023 |
College of Ceramics at Alfred University | T035122 |
$102,000.00
|
$100,980.00 |
07/16/2012 | 08/24/2012 | NEON SHOP VENTILATION AND SAFE | Contracts Not Subject to OSC Pre-Audit | 07/13/2012 |
College at Buffalo | T180187 |
$123,231.00
|
$123,231.00 |
05/02/2019 | 12/31/2019 | PROJECT M03550 CAUDELL SLP WIN | Contracts Not Subject to OSC Pre-Audit | 05/03/2019 |
Office of General Services - Design & Construction | D45849H |
$147,143.00
|
$139,658.00 |
05/16/2021 | 03/01/2024 | Provide facility wide CCTV/audio monitoring system and recording room Wende CF Erie County | Construction - Building | 05/16/2021 |
Office of General Services - Design & Construction | D46221H |
$149,700.00
|
$142,106.00 |
09/18/2020 | 06/30/2022 | Rehab Restrooms & Locker Rooms Buffalo Armory Masten Ave Erie County | Construction - Building | 09/18/2020 |
Office of General Services - Design & Construction | DEF055H |
$150,000.00
|
$33,693.36 |
08/23/2023 | 12/21/2023 | Repair chilled water piping in Bldg 18 on The State Office Building Campus in Albany County | Construction - Building | 09/25/2023 |
Office of General Services - Design & Construction | DEE615H |
$150,000.00
|
$130,512.09 |
07/23/2021 | 10/16/2022 | Replace failed refrigeration system Bldg 12 Freezer 24 Orleans CF Orleans county | Construction - Building | 08/31/2021 |
Office of General Services - Design & Construction | DED367H |
$150,000.00
|
$12,669.00 |
12/02/2016 | 04/01/2017 | Repair Failed Boiler - HVAC | Construction - Building | 02/07/2017 |
Office of General Services - Design & Construction | DEE420H |
$150,000.00
|
$31,230.00 |
08/24/2020 | 12/22/2020 | Repair deteriorated pipe E Block Auburn CF Cayuga County | Construction - Building | 10/30/2020 |
Office of General Services - Design & Construction | DEF111H |
$150,000.00
|
$41,025.84 |
12/11/2023 | 04/09/2024 | Repair water pipe Bldg. 24 State OB Campus Albany County | Construction - Building | 01/18/2024 |
Office of General Services - Design & Construction | DED278P |
$150,000.00
|
$33,627.00 |
08/16/2016 | 02/12/2017 | Investigate/repair gas leak, Bldg. 86, Gowanda CF. | Construction - Miscellaneous | 09/15/2016 |
Office of General Services - Design & Construction | DED653H |
$150,000.00
|
$16,733.00 |
11/17/2017 | 03/17/2018 | Provide Temporary Heat Bldg 12 Hutchings PC Onondaga County | Construction - Building | 12/15/2017 |
Office of General Services - Design & Construction | DEF047H |
$150,000.00
|
$59,313.22 |
08/16/2023 | 12/14/2023 | Repair chilled water piping at State OB Campus in Albany County | Construction - Building | 09/08/2023 |
Office of General Services - Design & Construction | D44127H |
$158,300.00
|
$150,781.00 |
08/04/2011 | 09/18/2012 | PROVIDE VENTILATION SYSTEM - ROOM 1-27, BLDG 4 LIVINGSTON CF | Construction - Building | 08/04/2011 |
Office of General Services - Design & Construction | D46062H |
$160,205.00
|
$157,352.00 |
08/06/2021 | 03/02/2023 | Provide building Fredonia Dunkirk Chautauqua County | Construction - Building | 08/06/2021 |
SUNY at Albany | T220019 |
$168,736.00
|
$168,736.00 |
10/07/2022 | 12/31/2023 | BUILDING 27 BASEMENT HEATING R | Contracts Not Subject to OSC Pre-Audit | 11/23/2022 |
Office of General Services - Design & Construction | D42795H |
$169,494.00
|
$167,713.00 |
10/19/2007 | 07/13/2012 | REPLACE SHOWER BLDGS. 9-11, 13-16 WENDE CF | Construction - Building | 12/07/2011 |
College at Fredonia | T000171 |
$173,169.00
|
$173,169.00 |
08/13/2010 | 04/15/2011 | PROJECT I00718 (05315) LOGRASSO HALL EMERGENCY GENERATOR REPLACEMENT | Contracts Not Subject to OSC Pre-Audit | 11/23/2010 |
Office of General Services - Design & Construction | D44928H |
$177,000.00
|
$165,743.00 |
02/11/2016 | 07/13/2017 | INSTALL EQUIPMENT & SERVICES, CULINARY ARTS PROGRAM, BLDG 51, ALBION CF | Construction - Building | 02/11/2016 |
Office of General Services - Design & Construction | D46000H |
$180,921.00
|
$180,134.00 |
03/29/2022 | 11/27/2023 | Replace generator Henderson-Smith State Office Building Clark County | Construction - Building | 03/30/2022 |