Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Department of Transportation | D037269 |
$38,747.69
|
$38,747.69 |
09/21/2016 | 03/18/2019 | POLE & ELECTRIC RELOCATION ROUTE 7 BRIDGE REPLACEMENT WORCESTER OTSEGO COUNTY | Construction - Utilities | 05/11/2017 |
Department of Transportation | D029992 |
$424,802.45
|
$424,802.45 |
10/30/2009 | 01/04/2015 | RELOCATE TRANSMISSION POLES, GLENRIDGE RD RECONST SARATOGA AND SCHENECTADY COS | Construction - Utilities | 03/19/2010 |
Department of Transportation | T021854 |
$11,032.67
|
$11,032.67 |
05/01/2005 | 05/01/2011 | RELOCATE EXISTING FACILITIES, I81 OVER HOXIE GORGE, BRIDGE REPL., CORTLAND CO. | Contracts Not Subject to OSC Pre-Audit | 07/18/2005 |
Department of Transportation | D032809 |
$165,607.67
|
$165,607.67 |
03/11/2010 | 03/11/2016 | RELOCATE OR ADJUST DISTRIBUTION AND APPURTENANCES FORT DRUM CONNECTOR ROAD, JEFFERSON COUNTY | Construction - Utilities | 03/17/2010 |
Department of Transportation | D032821 |
$22,032.45
|
$22,032.45 |
09/21/2009 | 09/20/2015 | RELOCATE POLES & APPURTENANCES ROUTE 11A ONONDAGA COUNTY | Construction - Utilities | 08/31/2010 |
Department of Transportation | D021825 |
$156,230.02
|
$156,230.02 |
04/15/2005 | 04/14/2011 | REPL OF AERIAL ELECTRIC DISTRIBUTION, I81 OVER SENECA TURNPIKE BRIDGE, ONONDAGA CO | Construction - Utilities | 05/13/2005 |
Department of Transportation | T014180 |
$13,270.92
|
$0.00 |
05/14/2001 | 05/14/2009 | RELOCATE POLES & AERIAL, MILLERSPORT HWY. CONST., ERIE CO., REF. #1A | Contracts Not Subject to OSC Pre-Audit | 06/25/2001 |
Department of Transportation | D034487 |
$335,509.00
|
$0.00 |
08/01/2012 | 07/31/2022 | REMOVAL/RELOCATION OF FACILITIES ON SOUTHWESTERN BLVD ROUTES NY 5 & US 20 IN CHAUTAUQUA & ERIE COS | Construction - Utilities | 07/23/2013 |
Department of Transportation | D034502 |
$83,585.00
|
$0.00 |
02/22/2013 | 02/21/2019 | RELOCATE UTILITY POLES AND ELECTRICAL LINES REHAB STATE ROUTE 11B AND CR ROUTE 5 FRANKLIN COUNTY | Construction - Utilities | 07/16/2013 |
Department of Transportation | T021576 |
$4,200.00
|
$0.00 |
09/17/2003 | 09/17/2011 | RELOCATE POLES AND AERIAL STATION CHAUTAUQUA CO | Contracts Not Subject to OSC Pre-Audit | 12/09/2003 |
Department of Transportation | T013993 |
$7,155.17
|
$0.00 |
04/27/2000 | 04/27/2001 | REMOVAL & INSTL OF LIGHTING, EGH YOUNGMAN HWY., REF. #1A, ERIE CO. | Contracts Not Subject to OSC Pre-Audit | 07/14/2000 |
Department of Transportation | T014441 |
$5,601.30
|
$0.00 |
12/20/2001 | 01/14/2010 | REMOVAL & RESETTING OF ST. LIGHT FAC, I90 BRIDGE REHAB, ERIE & NIAGARA COS | Contracts Not Subject to OSC Pre-Audit | 02/28/2003 |
Department of Transportation | T014447 |
$7,975.84
|
$0.00 |
12/13/2002 | 12/13/2009 | POLES & AERIAL RELOCATION, RT 31/GILL CREEK, TN OF NIAGARA NIAGARA CO | Contracts Not Subject to OSC Pre-Audit | 03/19/2003 |
Department of Transportation | T037334 |
$13,735.00
|
$7,684.41 |
11/01/2016 | 10/31/2026 | MOBILITY AND SAFETY SIDEWALK P | Contracts Not Subject to OSC Pre-Audit | 08/09/2017 |
Department of Transportation | D038903 |
$120,538.00
|
$0.00 |
04/05/2022 | 04/04/2027 | Private Property Reimbursable | Construction - Utilities | 06/30/2022 |
Department of Transportation | D037348 |
$490,000.00
|
$285,366.55 |
07/13/2017 | 07/12/2027 | POLE & DUCT BANK RELOCATION TEAL AVENUE & BEECH STREET SYRACUSE ONONDAGA COUNTY | Construction - Utilities | 12/04/2017 |
Department of Transportation | T029616 |
$20,000.00
|
$0.00 |
07/01/2006 | 07/02/2013 | RELOCATE POLE, CULVERT REPAIR/REPL., ALBANY, SARATOGA & WARREN COS. | Contracts Not Subject to OSC Pre-Audit | 06/19/2007 |
Department of Transportation | T014071 |
$7,672.97
|
$0.00 |
12/04/2000 | 12/04/2002 | REMOVAL & INSTL. OF WIRING, RT. 18 OVER 18 MILE CREEK, REF. #1A | Contracts Not Subject to OSC Pre-Audit | 01/10/2001 |
Department of Transportation | T014081 |
$3,878.28
|
$0.00 |
01/15/2001 | 01/15/2003 | RELOCATE POLES & AERIAL, RT. 75 TRAFFIC CIRCLE, ERIE CO., REF.#1A | Contracts Not Subject to OSC Pre-Audit | 02/16/2001 |
Department of Transportation | T036698 |
$1,500.00
|
$1,499.99 |
12/13/2013 | 12/12/2019 | RELOCATE AND/OR ADJUST UTILITY | Contracts Not Subject to OSC Pre-Audit | 03/24/2014 |
Department of Transportation | TA33261 |
$17,364.40
|
$17,364.40 |
01/20/2011 | 01/19/2018 | RELOCATE TWO POLES STEPHEN LAN | Contracts Not Subject to OSC Pre-Audit | 10/17/2012 |
Department of Transportation | D034455 |
$23,281.81
|
$23,281.81 |
04/15/2011 | 04/14/2016 | Reopen Relocate Natural Gas Pipeline Town of Glenville Schenectady County | Construction - Utilities | 01/14/2021 |
Department of Transportation | D036968 |
$487,841.64
|
$439,051.18 |
01/10/2014 | 01/09/2022 | RELOCATE 27 OVERHEAD ELECTRIC POLES RTE 281 CORTLANDVILLE CORTLAND COUNTY | Construction - Utilities | 07/03/2015 |
Department of Transportation | DA34329 |
$101,939.06
|
$101,939.06 |
11/23/2011 | 11/22/2016 | RELOCATE UTILITY POLES AND ATTACHMENTS RTE 22 BRIDGE REPLACEMENT WADHAMS ESSEX COUNTY | Construction - Utilities | 11/23/2012 |
Department of Transportation | D037457 |
$130,376.29
|
$130,376.29 |
12/01/2012 | 11/30/2022 | Utility Support Services Relocate Poles & Power Lines Sunset Ave & Champlin Ave Utica Oneida County | Construction - Utilities | 11/09/2018 |
Department of Transportation | D036691 |
$89,311.97
|
$79,421.84 |
06/12/2013 | 06/11/2023 | RELOCATE AERIAL LINES INTERSTATE 290 OVER RTE 265 ERIE COUNTY | Construction - Utilities | 05/02/2014 |
Department of Transportation | D034525 |
$48,813.91
|
$48,813.91 |
06/04/2013 | 06/21/2017 | REMOVAL RELOCATION REPLACEMENT RECONSTRUCTION UTILITY FACILITES & APPURTENANCES WESTERN REGION FOUR | Construction - Utilities | 09/12/2013 |
Department of Transportation | T037454 |
$7,797.86
|
$7,797.86 |
04/01/2018 | 08/09/2019 | CULVERT REPLACEMENT NY 417 AND | Contracts Not Subject to OSC Pre-Audit | 07/17/2018 |
Department of Transportation | DR32959 |
$60,489.19
|
$60,489.19 |
06/19/2008 | 06/18/2015 | RELOCATE 5 UTILITY POLES RTE 149 & 1 ON RTE 372 WARREN & WASHINGTON COUNTIES | Construction - Utilities | 06/08/2011 |
Department of Transportation | T029550 |
$45,848.88
|
$45,848.88 |
08/29/2006 | 08/29/2014 | RELOCATE POLES AND AERIAL LINES, RT. 62, T/O WHEATFIELD, NIAGARA CO. | Contracts Not Subject to OSC Pre-Audit | 02/08/2007 |
Department of Transportation | D021635 |
$0.01
|
$0.00 |
01/09/2004 | 01/09/2007 | RELOCATE POLES & UNDERGROUND ELECTRIC TN OF GREENWICH, WASH CO | Construction - Utilities | 05/07/2004 |
Department of Transportation | DA34305 |
$45,000.00
|
$45,000.00 |
02/09/2012 | 02/08/2019 | RELOCATE UNDERGROUND & AERIAL FACILITIES FULLER ROAD ALBANY COUNTY | Construction - Utilities | 11/23/2012 |
Department of Transportation | T036677 |
$30,804.61
|
$30,804.61 |
08/14/2013 | 08/13/2023 | RELOCATE OVERHEAD 46-KV LINE , | Contracts Not Subject to OSC Pre-Audit | 03/24/2014 |
Department of Transportation | X197583 |
$1.00
|
$0.00 |
05/27/2020 | 12/31/2100 | Permanent easement map 2 c parcel 2 Buffalo Erie County | Land Purchase | 07/28/2020 |
Department of Transportation | D032810 |
$706,348.40
|
$0.00 |
01/22/2010 | 01/21/2016 | RELOCATE OR ADJUST GAS MAIN FT DRUM CONNECTOR RD JEFFERSON COUNTY | Construction - Utilities | 03/17/2010 |
Department of Transportation | D029893 |
$53,517.00
|
$0.00 |
07/01/2008 | 07/01/2012 | RELOCATE GAS MAINS RTES 342 184 & 72 JEFFERSON & ST LAWRENCE COS | Construction - Utilities | 05/05/2009 |
Department of Transportation | T013907 |
$7,083.54
|
$0.00 |
01/27/2000 | 01/27/2001 | REMOVE ELECTRIC SERVICE, RT. 290 BRIDGE OVER LIMESTONE CREEK, REF. #2A, ONONDAGA CO. | Contracts Not Subject to OSC Pre-Audit | 03/06/2000 |
Department of Transportation | T039005 |
$48,996.93
|
$0.00 |
02/07/2023 | 02/06/2028 | Culvert Repairs US-11 | Contracts Not Subject to OSC Pre-Audit | 05/16/2023 |
Department of Transportation | D014440 |
$16,000.00
|
$0.00 |
12/02/2002 | 12/17/2009 | RELOCATE TRANSMISSION POLES | Construction - Utilities | 03/21/2003 |
Department of Transportation | T032894 |
$7,056.00
|
$0.00 |
09/09/2010 | 09/09/2016 | RELOCATE AERIAL 23KV SUB TRANSMISSION FACILITIES WATERTOWN JEFFERSON CO | Contracts Not Subject to OSC Pre-Audit | 10/25/2010 |
Department of Transportation | D038604 |
$790,000.00
|
$595,253.77 |
06/12/2019 | 06/11/2029 | Relocation Electric Facilities Albany Shaker Road I-87 Exit 4 Access Improvement Albany County | Construction - Utilities | 08/19/2019 |
Department of Transportation | T036937 |
$30,000.00
|
$25,272.09 |
01/28/2015 | 01/27/2025 | ROUTE 11,I-81 SB RAMP TO SYRAC | Contracts Not Subject to OSC Pre-Audit | 08/10/2015 |
Department of Transportation | T029509 |
$25,000.00
|
$25,000.00 |
06/01/2006 | 06/01/2011 | REMOVE, RELOCATE AND/OR ADJUST OVERHEAD ELECTRIC FACILITIES, I690 OVER RR, ONONDAGA CO. | Contracts Not Subject to OSC Pre-Audit | 12/01/2006 |
Department of Transportation | T030000 |
$13,954.62
|
$13,954.62 |
11/17/2009 | 11/17/2015 | RELOCATE OR AJUST AERIAL OGDENSBURG/PRESCOTT BR BORDER CROSSING ST LAWRENCE CO | Contracts Not Subject to OSC Pre-Audit | 02/22/2010 |
Department of Transportation | T029922 |
$33,065.49
|
$33,065.49 |
05/01/2009 | 05/01/2014 | RELOCATE POLES & AERIAL FACILITIES, BRIDGE REPL. MALTA AVE OVER I87, SARATOGA CO. | Contracts Not Subject to OSC Pre-Audit | 06/22/2009 |
Department of Transportation | T029574 |
$40,000.00
|
$40,000.00 |
05/01/2006 | 05/01/2013 | RELOCATE POLES, AERIAL & UNDERGROUND FACILITIES, I87 OVER RT. 155, TN OF COLONIE, ALBANY CO. | Contracts Not Subject to OSC Pre-Audit | 04/27/2007 |
Department of Transportation | T029587 |
$11,870.89
|
$11,870.89 |
12/17/2002 | 12/17/2012 | RELOCATE, REMOVE OR ADJUST AERIAL, RT. 37 OVER RAQUETTE RIVER, FRANKLIN CO. | Contracts Not Subject to OSC Pre-Audit | 05/22/2007 |
Department of Transportation | T032937 |
$8,305.89
|
$8,305.89 |
06/15/2007 | 06/15/2015 | RELOCATE POLES & OVERHEAD CONDUCTORS RT417 BRIDGE ALLEGANY CO | Contracts Not Subject to OSC Pre-Audit | 08/19/2011 |
Department of Transportation | D029589 |
$90,926.14
|
$90,926.14 |
06/01/2006 | 06/01/2011 | RELCATE ELERTICAL LINES I690 BRIDGE OVER CSX SYRACUSE, ONONDAGA COUNTY | Construction - Utilities | 07/02/2007 |
Department of Transportation | D032843 |
$51,589.98
|
$51,589.98 |
06/03/2009 | 06/03/2015 | RELOCATE AND/OR ADJUST AERIAL DISTRIBUTION RT 68 BRIDGE OVER TIBBITS CREEK ST LAWRENCE CO | Construction - Utilities | 08/12/2010 |