Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Office of General Services - Design & Construction | DEE768H |
$300,000.00
|
$83,774.28 |
02/14/2022 | 09/12/2022 | Repair Condensate Leak at Green Haven CF in Dutchess County | Construction - Building | 04/12/2022 |
Office of General Services - Design & Construction | DEE716P |
$300,000.00
|
$40,079.36 |
11/23/2021 | 10/07/2022 | Repair failed flange Eastern Correctional Facility Ulster County | Construction - Building | 12/24/2021 |
Office of General Services - Design & Construction | DED719H |
$100,000.00
|
$18,178.00 |
01/09/2018 | 07/08/2018 | Repair MTHW Pipe, Complex 2 Housing, Downstate CF, Dutchess County | Construction - Building | 02/28/2018 |
Office of General Services - Design & Construction | DEB927H |
$157,727.00
|
$126,501.00 |
05/22/2012 | 10/10/2012 | REPAIR CHILLER #3 PERRY B DURYEA BUILDING HAUPPAUGE NEW YORK | Construction - Building | 06/13/2012 |
Office of General Services - Design & Construction | DEE758P |
$100,000.00
|
$70,102.82 |
01/20/2022 | 05/20/2022 | Repair broken sewer line Green Haven CF Dutchess county | Construction - Building | 03/10/2022 |
Office of General Services - Design & Construction | DEC812H |
$300,000.00
|
$26,368.00 |
12/08/2014 | 04/07/2015 | Repair Boiler 1 & 2 - Powerplant @ Bronx PC | Construction - Building | 01/09/2015 |
Office of General Services - Design & Construction | DED887H |
$300,000.00
|
$210,206.00 |
08/20/2018 | 05/15/2019 | Repair Heat Exchangers Bldg 83 Pilgrim PC Suffolk County | Construction - Building | 09/14/2018 |
Office of General Services - Design & Construction | DEC876G |
$150,000.00
|
$9,171.00 |
03/05/2015 | 07/03/2015 | Correct Broken Water Line, Building 42, Pilgrim PC | Construction - Building | 03/25/2015 |
Office of General Services - Design & Construction | DED664H |
$300,000.00
|
$51,745.00 |
12/05/2017 | 06/03/2018 | Repair Medium Temperature Hot Water line to radiator Downstate CF Bldg. 4, Fishkill, Dutchess County | Construction - Building | 12/28/2017 |
Office of General Services - Design & Construction | DEE501C |
$150,000.00
|
$84,450.00 |
12/18/2020 | 04/17/2021 | Repair floor & floor drain Building 5 New York PI New York County | Construction - Building | 02/05/2021 |
Office of General Services - Design & Construction | DEE507G |
$300,000.00
|
$18,031.00 |
12/25/2020 | 04/24/2021 | Restore power & repair storm damage Rockland PC Rockland County | Construction - Building | 02/11/2021 |
Office of General Services - Design & Construction | DEE519P |
$150,000.00
|
$86,376.00 |
01/19/2021 | 05/19/2021 | Repair condensate lines building 122 Manhattan PC New York County | Construction - Building | 02/12/2021 |
Office of General Services - Design & Construction | DEE516P |
$250,000.00
|
$56,284.00 |
01/15/2021 | 07/14/2021 | Repair failed sump pump, Building 11, Bronx PC, Bronx Co | Construction - Building | 02/16/2021 |
Office of General Services - Design & Construction | DED982H |
$600,000.00
|
$593,367.00 |
12/05/2018 | 09/18/2019 | Replace Heating Lines Shawangunk CF Wallkill Ulster County | Construction - Building | 01/15/2019 |
Office of General Services - Design & Construction | DEC808H |
$300,000.00
|
$280,730.00 |
12/05/2014 | 06/03/2015 | PROVIDE ABOVE GROUND HEATING LIINE DOWNSTATE CF | Construction - Building | 01/14/2015 |
Office of General Services - Design & Construction | DED126P |
$600,000.00
|
$567,932.00 |
01/13/2016 | 05/12/2016 | Provide Int.&Ext. Renovations, | Contracts Not Subject to OSC Pre-Audit | 02/08/2016 |
Office of General Services - Design & Construction | DEF129H |
$250,000.00
|
$52,210.31 |
01/10/2024 | 05/09/2024 | Repair Heating Leak Otisville Correctional Facility Orange County | Construction - Building | 02/21/2024 |
Office of General Services - Design & Construction | DEF100P |
$150,000.00
|
$47,355.79 |
11/23/2023 | 03/22/2024 | Restore Plumbing Failures Lincoln Correctional Facility NY County | Construction - Building | 02/22/2024 |
Office of General Services - Design & Construction | DEF138G |
$300,000.00
|
$33,687.40 |
01/25/2024 | 05/24/2024 | Repair Sewer Line Bronx Armory Bronx County | Construction - Building | 02/21/2024 |
Office of General Services - Design & Construction | DEB589H |
$200,000.00
|
$177,924.00 |
07/26/2011 | 12/08/2011 | REPAIR LEAKING MAIN HIGH TEMP HOT WATER LINE PURCHASE SUC | Construction - Building | 01/25/2012 |
Office of General Services - Design & Construction | DEE891G |
$600,000.00
|
$264,530.52 |
10/27/2022 | 04/28/2023 | Repair leaking pipe Bldg 2 & 19 Kingsboro PC Brooklyn Kings County | Construction - Building | 11/25/2022 |
Office of General Services - Design & Construction | DEE553G |
$300,000.00
|
$135,686.12 |
03/29/2021 | 07/27/2021 | Repair Broken sewer line Bedford Hills CF | Construction - Building | 04/27/2021 |
Office of General Services - Design & Construction | DEE527N |
$500,000.00
|
$485,095.00 |
03/11/2021 | 10/04/2021 | Repair flood damage Building 500 Camp Smith Training Site Westchester County | Construction - Building | 04/29/2021 |
Office of General Services - Design & Construction | DEC094P |
$100,000.00
|
$12,120.00 |
12/03/2012 | 04/02/2013 | REMOVE HEATING OIL FROM UNDERGROUND TANKS BAYVIEW CORRECTIONAL FACILITY | Construction - Building | 12/26/2012 |
Office of General Services - Design & Construction | DEC800H |
$300,000.00
|
$293,283.00 |
12/05/2014 | 06/03/2015 | Emergency Contract - Provide Above Ground Heating Line - Downstate CF | Construction - Building | 01/14/2015 |
Office of General Services - Design & Construction | DEB598P |
$75,000.00
|
$12,001.00 |
07/22/2011 | 11/19/2011 | REPAIR BROKEN WATER LINE BUILDING 4 NEW YORK PI | Construction - Building | 08/31/2011 |
Office of General Services - Design & Construction | DEC739G |
$100,000.00
|
$63,333.00 |
09/18/2014 | 01/16/2015 | INVESTIGATE & CORRECT WATER MAIN LEAK BUILDING 29 ROCKLAND PC | Construction - Building | 10/15/2014 |
Office of General Services - Design & Construction | DED100G |
$200,000.00
|
$80,910.00 |
12/28/2015 | 04/26/2016 | Investigate & Repair Water Main Leak Post 18/Bldg 52, Sing Sing CF Westchester Co | Construction - Building | 02/11/2016 |
Office of General Services - Design & Construction | DED282H |
$150,000.00
|
$15,031.00 |
08/26/2016 | 12/24/2016 | Repair and Replace Steam Valve CK Post ATC Bldg 1. Region 1 | Construction - Building | 09/15/2016 |
Office of General Services - Design & Construction | DEC463H |
$300,000.00
|
$242,975.00 |
10/16/2013 | 10/22/2014 | REPAIR LEAKING STEAM PIPING FISHKILL CF | Construction - Building | 11/18/2013 |
Office of General Services - Design & Construction | DEC920G |
$200,000.00
|
$16,834.00 |
04/23/2015 | 08/21/2015 | CORRECT WATER MAIN BREAK, BLDG 68, CREEDMOOR PC | Construction - Building | 05/22/2015 |
Office of General Services - Design & Construction | DEB951N |
$100,000.00
|
$60,838.00 |
06/12/2012 | 04/02/2013 | INVESTIGATE REPAIR REPLACE FAILED FIRE STANDPIPE JAIMACA ARMORY | Construction - Building | 07/13/2012 |
Office of General Services - Design & Construction | DEC404H |
$300,000.00
|
$116,051.00 |
07/25/2013 | 11/22/2013 | REPAIR LEAKING MEDIUM TEMPERATURE HOT WATER LINE DOWNSTATE CF | Construction - Building | 08/29/2013 |
Office of General Services - Design & Construction | DEE209N |
$300,000.00
|
$245,206.00 |
12/16/2019 | 11/09/2021 | Repair Fire Suppression Tank Sing Sing CF Westchester County | Construction - Building | 01/08/2020 |
Office of General Services - Design & Construction | DEF179H |
$500,000.00
|
$0.00 |
04/16/2024 | 08/14/2024 | Repair failed chiller at NYS Police Salt Point in Dutchess County | Construction - Building | 05/06/2024 |
Office of General Services - Design & Construction | DED425G |
$300,000.00
|
$77,541.00 |
02/15/2017 | 06/15/2017 | Repair Water Main Breaks, Bldg's 41 & 21 Creedmoor PC | Construction - Building | 03/13/2017 |
Office of General Services - Design & Construction | DED420H |
$300,000.00
|
$156,716.00 |
02/10/2017 | 06/12/2017 | Investigate and repair heating pipe, Brooklyn DDSO, Kings County | Construction - Miscellaneous | 03/13/2017 |
Office of General Services - Design & Construction | DEC054H |
$75,000.00
|
$26,660.00 |
10/11/2012 | 02/08/2013 | REPAIR UG HEATING LINE BETWEEN BLDGS 122 & 120 @ OTISVILLE CF ORANGE CO | Construction - Building | 11/01/2012 |
Office of General Services - Design & Construction | DEE823P |
$300,000.00
|
$181,509.10 |
05/11/2022 | 11/30/2022 | Repair plumbing issues C block Woodbourne CF Sullivan County Region3 | Construction - Building | 06/17/2022 |
Office of General Services - Design & Construction | DED956P |
$150,000.00
|
$18,632.00 |
11/01/2018 | 04/30/2019 | Repair/Replace 12" Sanitary Line Sing Sing CF Westchester County | Construction - Building | 11/29/2018 |
Office of General Services - Design & Construction | DEE725P |
$200,000.00
|
$41,575.23 |
12/06/2021 | 04/05/2022 | Repair water line break Edgecombe CF New York County | Construction - Building | 01/14/2022 |
Office of General Services - Design & Construction | DED836G |
$600,000.00
|
$600,000.00 |
05/29/2018 | 08/15/2019 | Repair Leaking Steam Lines-Shawangunk CF Ulster County | Construction - Building | 08/01/2018 |
Office of General Services - Design & Construction | DEE232P |
$150,000.00
|
$63,391.00 |
11/19/2019 | 03/18/2020 | Repair Watermain Break Outside Bldg 5 Brooklyn DDSO Kings County | Construction - Building | 01/14/2020 |
Office of General Services - Design & Construction | DEE670H |
$300,000.00
|
$119,437.00 |
10/06/2021 | 08/19/2022 | Replace failed chiller pump and VFDs Buildings 81 82 83 Pilgrim PC Suffolk County | Construction - Building | 11/04/2021 |
Office of General Services - Design & Construction | DEC983G |
$200,000.00
|
$6,725.00 |
07/24/2015 | 01/20/2016 | Investigate & Correct Water Main Break, Bldg 3 South Beach PC, Richmond County | Construction - Building | 09/03/2015 |
Office of General Services - Design & Construction | DEF001G |
$300,000.00
|
$221,495.82 |
05/23/2023 | 03/18/2024 | Repair sanitary line at Otisville Correctional Facility Orange County | Construction - Building | 07/18/2023 |
Office of General Services - Design & Construction | DEF112P |
$400,000.00
|
$186,262.49 |
12/13/2023 | 10/11/2024 | Repair Sewage Pumps Building 12 Wallkill Correctional Facility Ulster County | Construction - Building | 12/27/2023 |
Office of General Services - Design & Construction | DEE734G |
$300,000.00
|
$114,774.22 |
12/16/2021 | 04/14/2022 | Repair failed sewer line at Bedford Hills CF Westchester County | Construction - Building | 01/14/2022 |
Office of General Services - Design & Construction | DEF021C |
$200,000.00
|
$56,470.72 |
07/12/2023 | 11/09/2023 | Repair wall damage building 40 at Highland Residential Center in Ulster County | Construction - Building | 07/31/2023 |
Office of General Services - Design & Construction | DEF090C |
$300,000.00
|
$0.00 |
03/11/2024 | 07/09/2024 | Repair and replace building roof 35 Nathan Kline RI Rockland County | Construction - Building | 04/30/2024 |