Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
Dormitory Authority of the State of New York | D190277 |
$5,803,000.00
|
$0.00 |
11/17/2015 | 07/01/2016 | PA Filed Contract-State University of New York College@Cortland DeGroat Residence Hall Renovations | Contracts Not Subject to OSC Pre-Audit | 11/24/2015 |
Dormitory Authority of the State of New York | D193849 |
$10,552,000.00
|
$0.00 |
08/08/2016 | 03/16/2018 | PA Filed Contract-Hutchings PC Buildings 1, 15&17 Rehabilitation w/Asbestos&Hazardous Mat. Abatement | Contracts Not Subject to OSC Pre-Audit | 08/17/2016 |
State University Construction Fund | T006919 |
$50,000.00
|
$50,000.00 |
07/10/2023 | 07/10/2024 | SUCF 071085 Construct New Lect | Contracts Not Subject to OSC Pre-Audit | 04/30/2024 |
State University Construction Fund | T006125 |
$1,275,194.00
|
$1,275,194.00 |
02/26/2015 | 08/15/2016 | SUCF 09395 ADA MODIFICATIONS | Contracts Not Subject to OSC Pre-Audit | 03/04/2015 |
State University Construction Fund | T005973 |
$10,120,055.00
|
$10,120,055.00 |
07/02/2012 | 03/04/2016 | SUCF 07A35 REHAB UNI UNION NTH | Contracts Not Subject to OSC Pre-Audit | 08/06/2012 |
State University Construction Fund | T006547 |
$2,078,225.00
|
$2,078,225.00 |
03/23/2020 | 08/14/2021 | SUCF091020 Rehabilitate West | Contracts Not Subject to OSC Pre-Audit | 03/24/2020 |
State University Construction Fund | T006314 |
$2,373,426.00
|
$2,373,426.00 |
04/07/2017 | 08/20/2019 | SUCF 25008 Replace Windows & | Contracts Not Subject to OSC Pre-Audit | 04/10/2017 |
State University Construction Fund | T005440 |
$4,935,556.00
|
$4,935,556.00 |
02/11/2009 | 06/15/2013 | BUILD ADDITION ON SCIENCE III/IV PLAZA #07A18 SUNY BINGHAMTON CAMPUS | Contracts Not Subject to OSC Pre-Audit | 05/05/2011 |
State University Construction Fund | T005922 |
$22,028,847.00
|
$22,028,847.00 |
02/28/2012 | 12/31/2016 | SUCF 06324 REHABILITATE BAILEY HALL SUC AT GENESEO | Contracts Not Subject to OSC Pre-Audit | 02/28/2012 |
State University Construction Fund | T006286 |
$11,313,609.00
|
$11,313,609.00 |
12/20/2016 | 07/01/2019 | SUCF 07A58 Rehabilitate Scien | Contracts Not Subject to OSC Pre-Audit | 12/23/2016 |
State University Construction Fund | T005269 |
$1,886,420.00
|
$1,886,420.00 |
06/26/2007 | 12/31/2012 | VERTICAL EXPANSION-INTERIOR FIT-OUT SUCF 15476 SYRACUSE HSC | Contracts Not Subject to OSC Pre-Audit | 01/25/2012 |
State University Construction Fund | T006477 |
$8,955,543.00
|
$8,955,543.00 |
03/19/2019 | 07/17/2021 | SUCF241013 Upgrade Mechanical | Contracts Not Subject to OSC Pre-Audit | 03/19/2019 |
State University Construction Fund | T005996 |
$1,030,631.00
|
$1,030,631.00 |
10/05/2012 | 12/21/2013 | CHANGE ORDER 4 FOR CONTRACT T0 | Contracts Not Subject to OSC Pre-Audit | 11/05/2012 |
State University Construction Fund | T006063 |
$9,665,308.00
|
$9,665,308.00 |
04/08/2014 | 12/31/2017 | CHANGE ORDER 21 FOR CONTRACT T | Contracts Not Subject to OSC Pre-Audit | 04/22/2014 |
State University Construction Fund | T006081 |
$28,020,231.00
|
$28,020,231.00 |
07/11/2014 | 08/15/2018 | CHANGE ORDER 2 FOR CONTRACT T0 | Contracts Not Subject to OSC Pre-Audit | 07/21/2014 |
State University Construction Fund | T005315 |
$47,413.00
|
$47,413.00 |
10/16/2007 | 08/03/2010 | ERECTION CHILD CARE CENTER/SCHOOL OF ED SUCF 04330 SUNY CORTLAND | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
State University Construction Fund | T005999 |
$47,240,680.00
|
$47,240,680.00 |
10/18/2012 | 05/21/2016 | CHANGE ORDER 31 FOR CONTRACT T | Contracts Not Subject to OSC Pre-Audit | 10/29/2012 |
State University Construction Fund | T006379 |
$5,017,954.00
|
$5,017,954.00 |
01/05/2018 | 10/31/2020 | SUCF241011 Upgrade Mechanical | Contracts Not Subject to OSC Pre-Audit | 01/11/2018 |
State University Construction Fund | T006125 |
$0.01
|
$0.00 |
02/26/2015 | 08/15/2016 | SUCF 09395 ADA Modifications | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |
State University Construction Fund | T006228 |
$34,587,057.00
|
$34,587,057.00 |
04/20/2016 | 12/31/2019 | SUCF 07A84 Construct School o | Contracts Not Subject to OSC Pre-Audit | 04/25/2016 |
State University Construction Fund | T005801 |
$26,713,315.00
|
$26,713,315.00 |
03/15/2011 | 10/30/2016 | SUCF 10340 PIEZ HALL RENOVATION SUNY OSWEGO | Contracts Not Subject to OSC Pre-Audit | 05/04/2011 |
State University Construction Fund | T006480 |
$2,809,775.00
|
$2,809,775.00 |
03/20/2019 | 08/16/2020 | SUCF091028 Site Improvements | Contracts Not Subject to OSC Pre-Audit | 03/28/2019 |
SUNY at Binghamton | T300251 |
$7,117,727.00
|
$7,117,726.96 |
08/08/2014 | 07/31/2015 | ENERGY R & D BUILDING - PHASE | Contracts Not Subject to OSC Pre-Audit | 08/12/2014 |
College at Oneonta | T990478 |
$1,297,013.48
|
$1,297,013.48 |
05/29/2019 | 06/12/2020 | CONSTRUCTION SERVICES FOR PROJ | Contracts Not Subject to OSC Pre-Audit | 06/02/2019 |
State University Construction Fund | T006469 |
$19,248,453.00
|
$19,248,453.00 |
01/16/2019 | 08/20/2022 | SUCF071013 Renovate Science I | Contracts Not Subject to OSC Pre-Audit | 01/18/2019 |