Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
College at Fredonia | T000218 |
$204,537.40
|
$204,537.40 |
04/23/2012 | 08/03/2012 | PROJECT D059FS (I00325) EISENH | Contracts Not Subject to OSC Pre-Audit | 04/25/2012 |
College at Fredonia | T000239 |
$189,820.00
|
$189,820.00 |
09/04/2013 | 09/30/2014 | PROJECT # D059FY - HEMMINGWAY | Contracts Not Subject to OSC Pre-Audit | 09/10/2013 |
SUNY at Buffalo | T500049 |
$1,738,715.00
|
$1,738,715.00 |
05/01/2014 | 05/31/2015 | PROJECT #2009-156B, MFAC TUNNE | Contracts Not Subject to OSC Pre-Audit | 04/12/2014 |
State University Construction Fund | T005957 |
$1,766,627.00
|
$1,766,627.00 |
05/29/2012 | 01/14/2015 | AJUSTMENT FOR CONTRACT T005957 | Contracts Not Subject to OSC Pre-Audit | 07/25/2012 |
College at Buffalo | T120001 |
$884,095.59
|
$881,619.89 |
03/14/2012 | 09/15/2012 | CAMPUS WEST RENOVATIONS FOR SURGE SPACE PROJECT#03422 | Contracts Not Subject to OSC Pre-Audit | 03/15/2012 |
State University Construction Fund | T006027 |
$1,799,648.00
|
$1,799,648.00 |
10/31/2013 | 05/04/2015 | CHANGE ORDER 11 FOR CONTRACT T | Contracts Not Subject to OSC Pre-Audit | 12/09/2013 |
SUNY at Buffalo | T500058 |
$414,426.00
|
$414,426.00 |
06/26/2015 | 02/14/2016 | UB STADIUM WEST GRANDSTAND REN | Contracts Not Subject to OSC Pre-Audit | 07/18/2015 |