Department/Facility | Contract Number | Current Contract Amount | Spending to Date | Contract Start Date | Contract End Date | Contract Description | Contract Type | Original Contract Approved/Filed Date |
---|---|---|---|---|---|---|---|---|
SUNY at Albany | T005177 |
$313,571.45
|
$312,938.75 |
04/08/2016 | 12/31/2016 | SEFCU ARENA ADA MODIFICATIONS | Contracts Not Subject to OSC Pre-Audit | 04/15/2016 |
Office of Parks Recreation & Historic Preservation | D004987 |
$84,683.00
|
$84,683.00 |
09/25/2017 | 12/24/2017 | SPAC Balcony Ramp Repairs Saratoga Spa State Park Saratoga County SA SPA 2017-01 | Construction - Building | 09/25/2017 |
Dormitory Authority of the State of New York | D220163 |
$1,131,560.00
|
$0.00 |
09/02/2022 | 07/18/2023 | PA filed contract Capital District Psychiatric Center phase 2 parking garage repairs | Contracts Not Subject to OSC Pre-Audit | 09/13/2022 |
Office of General Services - Design & Construction | D45795C |
$5,000,000.00
|
$4,042,528.00 |
07/16/2018 | 10/16/2021 | Masonry Repairs and Maintenance Various Albany Locations Albany County | Construction - Building | 07/16/2018 |
Office of General Services - Design & Construction | DED768C |
$100,000.00
|
$16,626.00 |
03/08/2018 | 09/04/2018 | Repair stairs, Complex 2E&F Housing Unit, Downstate CF, Dutchess County | Construction - Building | 04/19/2018 |
Office of General Services - Design & Construction | D43269C |
$4,191,864.00
|
$4,184,788.00 |
08/16/2007 | 04/23/2012 | MASONRY REPAIRS GNARESP | Construction - Building | 08/16/2007 |
Office of General Services - Design & Construction | D45149C |
$6,805,578.00
|
$6,779,249.00 |
07/06/2017 | 09/29/2019 | Provide Structural Repairs to East Parking Garage, Albany County | Construction - Building | 07/06/2017 |
Office of General Services - Design & Construction | D44349C |
$5,668,376.00
|
$5,588,275.44 |
07/31/2012 | 12/31/2015 | UNIT PRICE CONTRACT FOR MASONRY REPAIRS AT MULTIPLE SITES IN CAPITAL REGION | Construction - Building | 07/31/2012 |
Office of General Services - Design & Construction | D44860C |
$2,000,000.00
|
$1,993,548.00 |
04/29/2014 | 05/02/2017 | Plaza level masonry repairs ESP | Construction - Building | 04/29/2014 |
Office of General Services - Design & Construction | DEC252C |
$300,000.00
|
$212,088.00 |
05/01/2013 | 01/19/2015 | REPAIR UNSAFE VEHICLE BRIDGE SING SING CORRECTIONAL FACILITY | Construction - Building | 05/24/2013 |
Office of General Services - Design & Construction | D45231C |
$4,000,000.00
|
$3,999,999.00 |
05/19/2016 | 08/17/2019 | Masonry Repairs and Maintenance Empire State Plaza Albany NY Albany County | Construction - Building | 05/19/2016 |
Office of General Services - Design & Construction | D45980C |
$2,600,000.00
|
$2,222,138.20 |
11/06/2019 | 01/29/2023 | Provide Concrete Repairs Empire State Plaza Albany County | Construction - Building | 11/06/2019 |
Office of General Services - Design & Construction | DED472C |
$100,000.00
|
$7,873.00 |
05/21/2017 | 08/19/2017 | Provide Roof Protection & Stable Parapet Bldg 9 Hudson CF Columbia County | Construction - Building | 05/12/2017 |
Office of General Services - Design & Construction | D44108C |
$559,599.00
|
$557,295.00 |
03/16/2012 | 11/15/2013 | REHAB STEAM TUNNELS AND ENERGY PIPING MOHAWK CF | Construction - Building | 03/16/2012 |
State University Construction Fund | T006171 |
$348,104.00
|
$348,104.00 |
09/08/2015 | 01/06/2017 | SUCF 36126 REHAB PLAZA GARAGE | Contracts Not Subject to OSC Pre-Audit | 09/15/2015 |
State University Construction Fund | T006171 |
$0.01
|
$0.00 |
09/08/2015 | 01/06/2017 | SUCF 36126 Rehab Plaza Garage | Contracts Not Subject to OSC Pre-Audit | 12/21/2015 |
SUNY at Albany | D220123 |
$843,652.50
|
$799,547.72 |
05/02/2023 | 08/11/2023 | Tower façade repairs phase 1 at SUNY Albany | Construction - Building | 05/02/2023 |